What is Project B's Discounted Payback Period with a WACC of 9.75%?
YEAR CASH FLOWS
Project A Project B
0 -$1050 -$1050
1 675 360
2 650 360
3 360
4 360
Ans:- Discounted Payback Period is calculated by
= No of years before discounted payback recovery + (Initial Investment - Cumulative cash flow in the before recovery) / Discounted cash flow in the year after recovery
= 3 years + ($1050 - $899.22) / $248.13 = 3.61 years
Therefore, the discounted payback period for the project B is 3.61 years.
What is Project B's Discounted Payback Period with a WACC of 9.75%? YEAR CASH...
Question 12 6 pts What is Project A's Discounted Payback Period with a WACC of 7.75%? YEAR CASH FLOWS Project A Project B O -$1050 -$1050 1 675 360 2 650 360 3 360 360 HTML Editore BIA-A- IE 3 X XEE - OV C0DT 112pt Paragraph
Question 11 5 pts What is Project A's Payback with a WACC of 7.75%? YEAR CASH FLOWS Project A Project B 0 -$1050 -$1050 675 360 650 N 360 3 360 4 360 HTML Editore BI VA - A - I E3311XXSE V CDTi 12pt Paragraph
Question 10 5 pts What is Project B's Internal Rate of Return (IRR) with a WACC of 7.75%? YEAR CASH FLOWS Project A Project B 0 -$1050 -$1050 1 675 360 1 2 650 360 3 360 4 360 HTML Editora BTA - A - IEE 32. * DoPNV GODT 12pt Paragraph
What is Project A's Modified Internal Rate of Return with a WACC of 6.75%? YEAR CASH FLOWS Project A Project B 0 -$1050 -$1050 1 675 360 2 650 360 3 360 4 360
6 pts Question 17 What is Project A's Modified Internal Rate of Return with a WACC of 6.75%? YEAR CASH FLOWS Project A Project B 0 -$1050 -$1050 1 675 360 2 650 360 3 360 4 360 HTML Editora BIVA-AI EE311 x X, DE - 2 VE GODT 12pt Paragraph
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 - $180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 -$180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____ ?
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) 0 $(180) 1 100 2 65 3 100 4 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is _____ years. (Round to two decimal places.)
Gio's Restaurants is considering a project with the following expected cash flows: (Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(240) 0 1 92 65 3 92 4 90 If the project's appropriate discount rate is 8 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) O N M
What is the discounted payback period for the investment project that has the following cash flows, if the discount rate is 14 percent? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Year Cash Flows 0 -12,720 1 4,473 2 5,037 3 5,606 4 6,848