Question

Attempt d 1 Hour The Material Requirements Planning (MRP) system has decreased inventory levels and late deliveries. This tab
O Ounits O 5 units O 15 units O 35 units
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Item Period 1 2 3 4 5 6 7 8 9
Gross requirements 50 50 50 75 75 75 100 100 100
Scheduled receipts 140 0 0 0 0 0 0 0 0
Projected on hand 80 170 120 70 135 60 125 25 65 105
Net requirements 0 0 0 5 0 15 0 75 35
Planned order receipts 0 0 0 140 0 140 0 140 140
Planned order releases 0 0 140 0 140 0 140 140 0

Net requirements in period 6 is 15. option c is right

Add a comment
Know the answer?
Add Answer to:
Attempt d 1 Hour The Material Requirements Planning (MRP) system has decreased inventory levels and late...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled...

    calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...

  • Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct...

    Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...

  • Given the following product tree, complete the MRP records for parts X, Y, and Z. Note...

    Given the following product tree, complete the MRP records for parts X, Y, and Z. Note that parts X and Y have specified order quantities. FILL IN THE BLANKS Note: *Gross Requirements & Net Requirements are shown as negative because demand represents withdrawals from inventory Scheduled Receipts & Planned Order Receipts are shown as positive because production represents additions to inventory 1 | 2 | 3 | 4 | 5 -15 -10 -15 -10 -15 20 71 Part X LT:...

  • 1. Consider the necessary information for an MRP application provided On hand Lead Time 24 32 80 ...

    1. Consider the necessary information for an MRP application provided On hand Lead Time 24 32 80 2) E(3 C(2 Requirements include 125 units (80 firm orders and 45 forecast)。亿in week 10 plus the follo wing spares 10 23 17 20 25 Develop the MRP table for this problem. 2) Consider the dynamic demand of an end item following the MRP explosion ess. Time Demand 50 30 20 80 100 The order cost (setup) per order is S125. Inventory carrying...

  • Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and...

    Materials Requirements Planning (MRP) Franklin Fan’s two most profitable products are the ceiling fan (CF151) and the personal fan (PF032). With the rising popularity in home remodeling and personal comfort, Franklin Fan has enjoyed substantial demand for these two products. Last year, Kathryn Marley, the vice president of operations and supply chain management, approved the installation of a new MRP system. It is a first important step toward the eventual goal of a full-fledged ERP system. Marley worked closely with...

  • One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of tw...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • Homework: Chapter 14 Material Requirements Planning 11 of 20 (10 complete) HW Score: 42.75%, 8.55 of...

    Homework: Chapter 14 Material Requirements Planning 11 of 20 (10 complete) HW Score: 42.75%, 8.55 of 20 pl Score: 0 of 1 pt Question Help Problem 14.6 - Bookmatch The demand for subassembly S is 100 units in week 7. Each unit of Srequires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W. and 1 unit of X. Finally, each unit of U requires 2 units of...

  • Eighty units of end item X are needed at the beginning of week 6, and another...

    Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8 B(2) D(3) D(2) F(2) Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT