Question

If demand for the next several weeks is as shown, with average demand equal to 266,...

If demand for the next several weeks is as shown, with average demand equal to 266, how many orders will be placed using the lot for lot technique

Week 1 2 3 4 5
Demand 240 280 250 290 270

A. 1

B. 2

C. 4

D. 5

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Using Lot for lot (L4L) technique; order is given for the exact quantity required in each period to fulfill the demand. This technique minimizes average inventory. As the demand is for 5 periods, so ordered will be placed and received 5 times.

Week 1 2 3 4 5
Demand 240 280 250 290 270
Order Placed/received 240 280 250 290 270
Number of Orders 5

Therefore correct answer is option D. 5

Add a comment
Know the answer?
Add Answer to:
If demand for the next several weeks is as shown, with average demand equal to 266,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next...

    Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next six months MonthMay June July Aug Sept Oct Demand 260 240 240 240 270 290 The firm always plans to meet all demand. The firm currently has 260 workers capable of producing 260 units in a month (1 unit/worker). The workforce can be increased (at a cost of $650 (at a cost of $1,300 per worker). Inventory holding cost is $150 per unit per...

  • Imund Morgan: Attempt 1 A monopolistic competitor has the following information about cost and demand. Quantity...

    Imund Morgan: Attempt 1 A monopolistic competitor has the following information about cost and demand. Quantity Price (5) Total Revenue (5) Marginal Revenue (5) Total Cost (5) Marginal Cost (5) Average Cost(5) 15 15 175 7013 13 130 11 180 9 207 3.4 13.8 220 17 225 3.6 11.25 10 5 250 10 30 9 3 290 8 9.67 3359 9.57 385 10 9.63 0 16 10.33 113 What will this firm's profits equal in the short run? nd Morgan:...

  • The current aggregate demand requirements for a firm are shown below for the next six months:...

    The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct Demand 270 250 250 250 280 300 The firm always plans to meet all demand. The firm currently has 270 workers capable of producing 270 units in a month (1 unit/worker). The workforce can be increased (at a cost of $700 per worker) or decreased (at a cost of $1,400 per worker). Inventory holding cost is $175...

  • 1) A Chemical factory is located next to a farm. This plant produces several types of...

    1) A Chemical factory is located next to a farm. This plant produces several types of adhesives. Airborne emissions from the production of chemical factory damage crops on the farm. The private marginal benefits of producing adhesives (P = 360 – 0.4Q), the private marginal costs (P = 90+ 0.29), and the external damage (P = 0.30)is as follows: 200 300 400 500 600 700 800 900 Tons of 100 adhesives PMB 320 PMC 1 10 EMC 140 0 280...

  • SCM 301

    The forecasts generated by three forecasting methods and actual demand for the Torrance Company are as follows:Month        Demand        Forecast 1        Forecast 2      Forecast 31                 269                 275                   268                  2802                 289                 266                   287                  2953                 294                 290                   292                  2904                 278                 284                   298                  2805                 268                 270                   274                  2706                 269                 268                   270                  260Compute the MSE and MAD for each forecasting method. Which method is better?...

  • NO HANDWRITTEN ANSWERS PLEASE! INCLUDE FORMULAS FOR BOTH MAD AND MSE PLEASE! The forecasts generated by...

    NO HANDWRITTEN ANSWERS PLEASE! INCLUDE FORMULAS FOR BOTH MAD AND MSE PLEASE! The forecasts generated by three forecasting methods and actual demand for the Torrance Company are as follows: Month        Demand        Forecast 1        Forecast 2      Forecast 3 1                 269                 275                   268                  280 2                 289                 266                   287                  295 3                 294                 290                   292                  290 4                 278                 284                   298                  280 5                 268                 270                   274                  270 6...

  • Using the BOM shown below, 2 weeks B (4) 1 week C (4) 1 week D(4)...

    Using the BOM shown below, 2 weeks B (4) 1 week C (4) 1 week D(4) 2 weeks F(4) E (2) 4.9 weeks C(4) 1 week E (2) 4.9 weeks 5.9 weeks a. How many of part E will be needed if 24 units of end item A are needed? Number of parts needed b. How many part Cs will be needed? Number of parts needed

  • The details of the hard drive sales for the past 6 weeks are shown in the...

    The details of the hard drive sales for the past 6 weeks are shown in the table below. The time series appears to be relatively stable, without trend, seasonal, or cyclical effects. You have been told to use 2 period weighted moving average estimation technique to help in forecasting the needs for next week. (k =2 with weights 0.8, 0.2) Week Units sold 88 44 54 65 572 6 85 You are being asked to help forecast for week 7,...

  • Question 13 (15 points) Consider the following data concerning the performance of a forecasting method. 200...

    Question 13 (15 points) Consider the following data concerning the performance of a forecasting method. 200 280 Month November December January February March Actual demand 300 270 250 310 Forecast 270 260 270 250 a. Forecast the demand for the month of April using three month moving average method. (5 points) b. Forecast the demand for the month of April using weighted moving average method. Weights for last three months (t-1, -2, and t-3) are 0.5, 0.3, and 0.2 respectively....

  • answer 1-3 please don't copy from previous post. good luck Problems #3, 5, 7 (P3) The...

    answer 1-3 please don't copy from previous post. good luck Problems #3, 5, 7 (P3) The owner of the Chocolate Outlet Store wants to forecast chocolate demand. Demand for the preceding four years is shown in the following table: Year Demand (Pounds) 1 68,800 2 71,000 3 75,500 4 71,200 Forecast demand for Year 5 using the following approaches: (1) a three-year moving average; (2) a three-year weighted moving average using .40 for Year 4, .20 for Year 3, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT