Using the BOM shown below, 2 weeks B (4) 1 week C (4) 1 week D(4) 2 weeks F(4) E (2) 4.9 weeks C(4) 1 week E (2) 4.9 weeks 5.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a. 1 unit of A requires 4 units of B,

Hence, 24 units of A will need, 24 x 4 units of B

1 unit of B requires 2 units of E, Hence, 24 x 4 units of B requires 24 x 4 x 2 units of E.

Again, 1 unit of A requires 4 units of D, Hence, 24 units of A require 24 x 4 units of D,

1 unit of D require 2 units of E, Hence, 24 x 4 units of D require 24 x 4 x 2 units of E.

Total units of E required for 24 units of A = 24 x 4 x 2 + 24 x 4 x 2 = 384 units of E

b. 1 unit of A require 4 units of C, Hence, 24 units of A require 24 x 4 units of C

Again,

1 unit of A require 4 units of D, Hence, 24 units of A require 24 x 4 units of D

1 unit of D require 4 units of C, Hence, 24 x 4 units of D require 24 x 4 x 4 units of C.

Total units of C required = 24 x 4 + 24 x 4 x 4 = 480 units of C are required.

Add a comment
Know the answer?
Add Answer to:
Using the BOM shown below, 2 weeks B (4) 1 week C (4) 1 week D(4)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. Based on the BOM shown below, how many units of part F will be needed...

    4. Based on the BOM shown below, how many units of part F will be needed if 15 units of end item A are needed? If the company decided to purchase part D from suppliers, how would th change? Assuming part D is purchased, how many units of part F are needed to make 15 units of end item A? 2 weeks B (1) 1 week C (4) 1 week D (2) 2 weeks D (3) 2 weeks G (2)...

  • Based on the BOM shown below, how many of part J will be needed if 40...

    Based on the BOM shown below, how many of part J will be needed if 40 units of end item A are needed? Managers have decided to outsource part G. Revised the BOM for end item A, assuming that item G is now purchase from a supplier. How many of part J will now be needed if 40 units of end item A are needed? Show all work. em A, assuming that item G is now purchased from a suppliet....

  • 3. (30 points) Consider the BOM tree of a sub-assembly, namely A. Land time (LT) consists...

    3. (30 points) Consider the BOM tree of a sub-assembly, namely A. Land time (LT) consists of estimates for setup time, processing time, materials handling time between operations or waiting time, depending on the item type. Items (B,C,D,E,F,G) belong to one of the followings: raw materials, purchased parts of manufactured parts. LT is given in terms of weeks. Suppose that there is no on-hand inventory and no scheduled receipts for all items. How many units of items E, D, and...

  • The MPS for the product shown calls for 75 units to be produced in weeks 2...

    The MPS for the product shown calls for 75 units to be produced in weeks 2 and 4. Item B has a lead time of 1 week, the batch size is 200, and there are currently 100 units of inventory. A planned order release for B will be needed in week(s) ________. a. 1 b. 2 c. 3 d. 1 and 2 e. 1 and 3

  • The MPS for the product shown calls for 75 units to be produced in weeks 2...

    The MPS for the product shown calls for 75 units to be produced in weeks 2 and 4. Item B has a lead time of 1 week, the batch size is 200, and there are currently 100 units of inventory. A planned order release for B will be needed in week(s) ________. a. 1 b. 2 c. 3 d. 1 and 2 e. 1 and 3 A B (3) ะก D (2)

  • Consider the bill of materials (BOM) shown to the right.

    Consider the bill of materials (BOM) shown to the right. a. How many immediate parents (one level above) does item I have? How many immediate parents does item E have? Item I has 2 immediate parent(s) and item E has 2 immediate parent(s) (Enter your responses as integers.) b. How many unique components does product A have at all levels? Product A has  unique components. (Enter your response as an integer.) c. Which of the components are purchased items?  Items F,...

  • The following table lists the components needed to assemble an end item, lead times (in weeks),...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand L12), c(1),x(3) B(2), 33) G(2), 8(2) H(4), B(2) 13 16 21 29 a. f 43 unts of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week...

  • The following table lists the components needed to assemble an end item, lead times (in weeks),...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand on Hand Iten End Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units C b. An order for the end item is scheduled to be shipped at...

  • The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on h...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ts Direct C End rded B(2), 3(3) G(2), B(2) H(4), B(2) 12 21 32 103 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) 405 0 Additional units b. An order for the end item is scheduled to be shipped...

  • The following table lists the components needed to assemble an end item, lead times (in weeks),...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT