Question

The following table lists the components needed to assemble an end item, lead times (in weeks),...

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item Lead Time Amount
on Hand
Direct Components
End 3 0 L(2), C(1), K(3)
L 3 12 B(2), J(3)
C 4 15 G(2), B(2)
K 4 21 H(4), B(2)
B 3 32
J 4 27
G 4 5
H 3 0


a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)

Additional units             

b. An order for the end item is scheduled to be shipped at the start of week 17. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)

The latest week  

0 0
Add a comment Improve this question Transcribed image text
Answer #1

keauired to make u3 unik end ftem. 43 x2 mount L on hand 12 units Additional units 6-12 4 units &imitany Additional units Add6) End tem must de shipped endur for In week 7 end item must stant in week (-3) - oeet 4 in nleek 4 To make end ?fem, L,C)K m

Add a comment
Know the answer?
Add Answer to:
The following table lists the components needed to assemble an end item, lead times (in weeks),...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT