The following table lists the components needed to assemble an
end item, lead times (in weeks), and quantities on hand.
Item | Lead Time | Amount on Hand |
Direct Components | |||
End | 3 | 0 | L(2), C(1), K(3) | |||
L | 3 | 12 | B(2), J(3) | |||
C | 4 | 15 | G(2), B(2) | |||
K | 4 | 21 | H(4), B(2) | |||
B | 3 | 32 | ||||
J | 4 | 27 | ||||
G | 4 | 5 | ||||
H | 3 | 0 | ||||
a. If 43 units of the end item are to be
assembled, how many additional units of B are needed?
(Hint: You don’t need to develop an MRP plan.)
Additional units
b. An order for the end item is scheduled to be
shipped at the start of week 17. What is the latest week that the
order can be started and still be ready to ship on time?
(Hint: You don’t need to develop an MRP plan.)
The latest week
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand on Hand Iten End Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units C b. An order for the end item is scheduled to be shipped at...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ts Direct C End rded B(2), 3(3) G(2), B(2) H(4), B(2) 12 21 32 103 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) 405 0 Additional units b. An order for the end item is scheduled to be shipped...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand L12), c(1),x(3) B(2), 33) G(2), 8(2) H(4), B(2) 13 16 21 29 a. f 43 unts of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 1 1 1 2 1 2 Amount on hand 0 11 8 26 12 30 7 0 A. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. E Item LT (wk) Amount on hand End 2 0 B 2 11 C 3 8 D 3 26 1 F 2. 31 G 1 3 INO 12 End Item B (2) с D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 19 units of the end item are to be assembled, how many additional units...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End H Item LT (W) Amount on hand 1 B 3 10 с 4 9 D 4 25 E 2 11 F 1 26 G 2 7 1 0 o End Item B12) с D (3) E (2) F (3) G 21 E (2) H14) E (2) a. If 24 units of the end item are to be assembled, how many additional...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G Item LT (wk) Amount on hand End 2 0 B 2 11 C 1 8 D 1 26 E 1 12 F 2 30 1 H 2 0 7 End Item B (2) C D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 21 units of the end item are to be assembled, how many...
The following table lists the components needed to assemble an
end item, lead times, and quantities on hand.
Item
End
B
C
D
E
F
G
H
LT (wk)
2
2
2
2
1
2
1
2
Amount on hand
0
11
8
26
12
28
6
0
a. If 20 units of the end item are to be
assembled, how many additional units of E are needed?
(Hint: You don't need to develop an MRP plan to determine
this.)...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End с D E F G H Item LT (wk) Amount on hand 1 B 3 7 1 1 1 1 1 1 0 12 22 8 29 5 0 End Item B (2) C D (3) E (2) F (3) G (2) E (2) H (4) E (2) a. If 21 units of the end item are to be assembled, how...