The following table lists the components needed to assemble an
end item, lead times, and quantities on hand.
Item | End | B | C | D | E | F | G | H |
LT (wk) | 2 | 2 | 2 | 2 | 1 | 2 | 1 | 2 |
Amount on hand | 0 | 11 | 8 | 26 | 12 | 28 | 6 | 0 |
a. If 20 units of the end item are to be
assembled, how many additional units of E are needed?
(Hint: You don't need to develop an MRP plan to determine
this.)
Additional units
b. An order for the end item is scheduled to be
shipped at the start of week 17. What is the latest week that the
order can be started and still be ready to ship on time?
(Hint: You don't need to develop an MRP plan for this part
either.)
The latest week
Answer a: 138 additional units of E are needed
Explanation:
Item | Relation | Requirement= relation *net requirement of related part | Inventory | net requirement= requirement- Inventory |
End, A | 20 | 0 | 20 | |
B | 2A | 40 | 11 | 29 |
C | 1A | 20 | 8 | 12 |
D | 3A | 60 | 26 | 34 |
E | 2B +2C+2D | 150 | 12 | 138 |
Answer b: the latest week to start is 11
Explanation:
Start time= | 17 | |
BOM path | Total lead time= sum of all lead times in a path | Start time= Start week -total lead time of path |
ABE | 2+2+1= 5 | 17-5= 12 |
ABF | 2+2+2= 6 | 17-6= 11 |
ACG | 5 | 12 |
ACE | 5 | 12 |
ADH | 6 | 11 |
ADE | 5 | 12 |
we have to start by 11th week.
Please ask, if you have any doubts through the comment section. Do rate the answer
The following table lists the components needed to assemble an end item, lead times, and quantities...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 1 1 1 2 1 2 Amount on hand 0 11 8 26 12 30 7 0 A. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End H Item LT (W) Amount on hand 1 B 3 10 с 4 9 D 4 25 E 2 11 F 1 26 G 2 7 1 0 o End Item B12) с D (3) E (2) F (3) G 21 E (2) H14) E (2) a. If 24 units of the end item are to be assembled, how many additional...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G Item LT (wk) Amount on hand End 2 0 B 2 11 C 1 8 D 1 26 E 1 12 F 2 30 1 H 2 0 7 End Item B (2) C D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 21 units of the end item are to be assembled, how many...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. E Item LT (wk) Amount on hand End 2 0 B 2 11 C 3 8 D 3 26 1 F 2. 31 G 1 3 INO 12 End Item B (2) с D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 19 units of the end item are to be assembled, how many additional units...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End с D E F G H Item LT (wk) Amount on hand 1 B 3 7 1 1 1 1 1 1 0 12 22 8 29 5 0 End Item B (2) C D (3) E (2) F (3) G (2) E (2) H (4) E (2) a. If 21 units of the end item are to be assembled, how...
Problem 12-2 The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End E F Item LT (wk) Amount on hand 1 B 3 7 с 3 12 D 3 22 1 1 G 1 6 H 1 0 0 8 32 End Item B (2) C D (3) E (2) F (3) G (2) E (2) H14) E (2) a. If 23 units of the end item are to be assembled,...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ts Direct C End rded B(2), 3(3) G(2), B(2) H(4), B(2) 12 21 32 103 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) 405 0 Additional units b. An order for the end item is scheduled to be shipped...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand on Hand Iten End Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units C b. An order for the end item is scheduled to be shipped at...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand L12), c(1),x(3) B(2), 33) G(2), 8(2) H(4), B(2) 13 16 21 29 a. f 43 unts of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week...
Exam 3 Help The following table lists the components needed to assemble an end item, lead times, and quantities on hand 30 E G Item LT (W) Amount on hand End 3 B 1 9 С 3 10 D 3 24 1 F 3 28 1 H 3 0 10 5 10 Endom D FO E121 6. If 19 units of the end item are to be assembled, how many additional units of E are needed? (Hint You don't need...