Question

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ts Di
1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

a)

Net requirement of L = 2*End item - On hand stock of L = 2*43 - 12 = 74

Net requirement of C = 1*End item - On hand stock of C = 1*43 - 15 = 28

Net requirement of K = 3*End item - On hand stock of K = 3*43 - 21 = 108

Net requirement of B = 2*(Net requirement of L + Net requirement of C + Net requirement of K) - On hand stock of B = 2*(74+28+108) - 32 = 388

b)

Item needs to be shipped in week 17 start.

Lead time of End item is 3 weeks, so L, C and K must be available 3 weeks prior which is 17-3 = Week 14

Lead time of C and K is 4 weeks, so it must start by 14-4 = Week 10

Now, J and G has lead time of 4 weeks, so latest start week = 10-4 = Week 6

Ans Week 6

Add a comment
Know the answer?
Add Answer to:
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on h...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT