The NPV is computed as shown below:
= Initial investment + Present value of future cash flows
Present value is computed as follows:
= Future value / (1 + r)n
So, the NPV is computed as follows:
= - $ 1,600 + $ 470 / 1.08 + $ 600 / 1.082 + $ 640 / 1.083 + $ 720 / 1.084 + $ 220 / 1.085
= $ 536.59 Approximately
Feel free to ask in case of any query relating to this question
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign Do not round intermediate calculations and round your final answer to 2 decimal places.) Protect Time: Cash flow: $1,900 $530 $660 $700 $780 $280 NPV Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$2,900 $650 $780 $820 $900 $400
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$1,200 $390 $520 $560 $640 $140
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: −$1,900 $530 $660 $700 $780 $280 NPV? Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: Cash flow: -$1,300 $470 $1,780 $580 $420 -$160 NPV Should the project be accepted or rejected? rejected accepted
Compute the NPV for Project K if the appropriate cost of capital is 6 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: –$11,800 $5,900 $6,900 $6,900 $5,900 –$14,800
Compute the NPV for Project K if the appropriate cost of capital is 5 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: Cash flow: 0 1 $10,200 $5,100 2 $6,100 3 $6,100 4 $5,100 5 $10,200 NPV Should the project be accepted or rejected? accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,100 $3,650 $4,480 $1,820 $600
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -$8,100 $3,370 $4,200 $1,540 $320 NPV
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,400 $3,710 $4,540 $1,880 $660 NPV $