Question

First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at t
Day Q Job 1 2 3 4 5 6 7 8 9 10 11 E - - - - - - - 1 F 1 - - - 1 G Now
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer -

Jobs Planned Start Planned End Actual Start Actual end Reason
D 2 8.5 2 6.5 Since, Job D is 2 day ahead of scheduled time at the end of the 4 day. So, it can be finished 2 days prior to the planned end date.
E 1 4 1 4 Job E was on time
F 3 8 3.5 8.5 Due to maintenance force Job F start by delay of 0.5 day and hence will finish 0.5 day late
G 2 7 2 8 The Job G was due to start on 2 day and would take 6 days to finish but at end of the 4th day, it was 1 day behind the schedule. Therefore it will finish 1 day ahead of the planned day.

Days Jobs 1 2 3 4 5 6 7 8 9 10 11 D E za → 다 G Actual Planned - 4

Add a comment
Know the answer?
Add Answer to:
First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT