Question
a) For the existing layout, the cumulative "load x distance" or "movement cost" = ______ feet.
b) Based on the flows shown in the matrix, one should expect that the centers A and __ will be next to each other as they have the highest numbers of moves between each other.
c) Based on the flows shown in the matrix, one should expect that the centers C and __ will be next to each other as they have the second highest numbers of moves between each other.
d) The aim is to improve the layout so that the total "movement cost" can be reduced. Functional locations for A and D have been fixed. In the improved layout, the work center that should be located between them is __.
e) The cumulative distance based on the overall movement of parts between work centers for this layout = _______ feet.


Munson Manufacturing, in Gainesville, Florida, wants to arrange its four work centers so as to minimize interdepartmental par
0 1
Add a comment Improve this question Transcribed image text
Answer #1

a.

Distance between A & B = 30

Distance between A & C = 60

Distance between A & D = 90

Distance between B & C = 30

Distance between B & D = 60

Distance between D & C = 30

Movement cost = \sum Load * Distance

Movement cost = 30*480 + 60*500 + 90*60 + 30*350 + 30*200 + 30*750 = 88800

b.

Moves between A & B = 480 + 350 = 830

Moves between A & C = 500

Moves between A & D = 60

Moves between B & C = 200

Moves between B & D = 0

Moves between D & C = 750

Based on the flows shown in the matrix, one should expect that the center's A and B will be next to each other as they have the highest numbers of moves between each other. (830 Moves)

c.

Based on the flows shown in the matrix, one should expect that centers C and D will be next to each other as they have the second highest numbers of moves between each other. (750 Moves)

d.

As we can see that, third highest moves are between A & C (500). These work centres should be close to each other.

Improved layout as follows:

B A C D

In the improved layout, the work center that should be located between them is C

e.

.According to new layout,

Distance between A & B = 30

Distance between A & C = 30

Distance between A & D = 60

Distance between B & C = 60

Distance between B & D = 90

Distance between D & C = 30

Movement cost for this layout = \sum Load * Distance

Movement cost for this layout = 30*480 + 30*500 + 60*60 + 30*350 + 60*200 + 30*750 = 78000

The cumulative distance based on the overall movement of parts between work centers for this layout = ____78000___ feet.

Add a comment
Know the answer?
Add Answer to:
a) For the existing layout, the cumulative "load x distance" or "movement cost" = ______ feet....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Munson Manufacturing, in Gainesville, Florida, wants to arrange its four work centers so as to minimize...

    Munson Manufacturing, in Gainesville, Florida, wants to arrange its four work centers so as to minimize interdepartmental parts handling costs. The flows and existing facility layout are shown in the figures below Figure 1. Parts Moved Between Work Centers 480 550 200 325 750 0 Figure 2. Existing Layout 30-1 a) For the existing layout, the cumulative "load x distance" or "movement cost"-feet (enter your response as a whole number) B) The highest flow that exists between any two work...

  • on the work are shown in the buty nithe number of loads of material that have...

    on the work are shown in the buty nithe number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix an the left below. Finally, Cransay alsa davnoped a matrix ha indicate distances Roy Cressay Enterprises, a machine shop, is planning to move to a new larger location. The new building wil be 60 feet long by 40 feet wide. Creasey envisions the building as having...

  • Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The...

    Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room Room Room Room Room Room 5 His foreman has completed a...

  • Roy Creasey​ Enterprises, a machine​ shop, is planning to move to a​ new, larger location. The new building will be 60 f...

    Roy Creasey​ Enterprises, a machine​ shop, is planning to move to a​ new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production​ areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room 1Room 2 Room 3 Room 4 Room 5 Room 6 His...

  • Hello, Need to see the solution. How they got these numbers. Roy Creasey Enterprises, a machine...

    Hello, Need to see the solution. How they got these numbers. Roy Creasey Enterprises, a machine shop, is planning to move to a new larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic Room...

  • For the layout that you have developed based on the preassigned work stations for processes C, D,...

    For the layout that you have developed based on the preassigned work stations for processes C, D, E, the cumulative “load x distance” or “movement cost” = ... feet? Six processes are to be laid out in six areas along a long corridor at Rita Gibson Accounting Services in Daytona Beach. The distance between adjacent work centers is 40 feet. The number of trips between work centers is given in the following table: Figure 1. Interstation Activity Mix Trips between...

  • PLEASE SHOW ALL EXCEL FORMULAS USED FOR EACH CALCULATIONS. A STEP BY STEP WALKTHROUGH OF HOW TO DO THE PROBLEM. Thank you so much for your help! Hours   Feet   Elevator   Elevator code 24.00   545   Y...

    PLEASE SHOW ALL EXCEL FORMULAS USED FOR EACH CALCULATIONS. A STEP BY STEP WALKTHROUGH OF HOW TO DO THE PROBLEM. Thank you so much for your help! Hours   Feet   Elevator   Elevator code 24.00   545   Yes   1 13.50   400   Yes   1 26.25   562   No   0 25.00   540   No   0 9.00   220   Yes   1 20.00   344   Yes   1 22.00   569   Yes   1 11.25   340   Yes   1 50.00   900   Yes   1 12.00   285   Yes   1 38.75   865   Yes   1 40.00   831   Yes   1...

  • A certain mutual fund invests in both U.S. and foreign markets. Let x be a random...

    A certain mutual fund invests in both U.S. and foreign markets. Let x be a random variable that represents the monthly percentage return for the fund. Assume x has mean μ = 1.9% and standard deviation σ = 0.7%. (a) The fund has over 250 stocks that combine together to give the overall monthly percentage return x. We can consider the monthly return of the stocks in the fund to be a sample from the population of monthly returns of...

  • Prokaryotic Translation Order each picture set, from the initiation of translation to the termination of translation...

    Prokaryotic Translation Order each picture set, from the initiation of translation to the termination of translation T себя у ч н н н н нонно N-с-с-N-с-с-N-с-с -с-с н R. o R. o R. o \ R, O н нннннно - C-C-N - C-C-N-C-C-N-с-с R 0 R₂0 R₂0 Ro Peptide bond H H H 0 N-C-C-N-C-C-N-C-C Ý ß o R o Rö | H H H H H Hà H H ) N-C-C-N-C-C-N-C-C-N-C-C H R o Ro R₂0 RO Before it...

  • Let’s build a dynamic string tokenizer! Start with the existing template and work on the areas...

    Let’s build a dynamic string tokenizer! Start with the existing template and work on the areas marked with TODO in the comments: Homework 8 Template.c Note: If you turn the template back into me without adding any original work you will receive a 0. By itself the template does nothing. You need to fill in the code to dynamically allocate an array of strings that are returned to the user. Remember: A string is an array. A tokenizer goes through...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT