Since Drills and Grinders have maximum number of movements between them ( 145), they should be placed adjacent to each other.
The next highest movement is between Material and Welding ( 125) so they should also be placed adjacent.
Movement from materials = 100x20+50x40+50x20= 5000
Movment from Welding = 25x20+50x20= 1500
Movemen from Drills = 20x40+45x20 = 1700
Movement from Lathes = 20x20+20x20 =800
Movement from Grinders = 50x20+100x20=3000
Movement from Benders =15 x20+25x20 =800
Total movement = sum of all values = 12800
on the work are shown in the buty nithe number of loads of material that have...
Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room Room Room Room Room Room 5 His foreman has completed a...
Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic. Room 1Room 2 Room 3 Room 4 Room 5 Room 6 His...
Hello, Need to see the solution. How they got these numbers. Roy Creasey Enterprises, a machine shop, is planning to move to a new larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic Room...
.. 9.4 Roy Creasey Enterprises, a machine shop, is planning to move to a new larger location. The new building will be 60 feet Tong by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic Building Schematic (with work areas 1-6) His foreman has completed...
For the layout that you have developed based on the preassigned work stations for processes C, D, E, the cumulative “load x distance” or “movement cost” = ... feet? Six processes are to be laid out in six areas along a long corridor at Rita Gibson Accounting Services in Daytona Beach. The distance between adjacent work centers is 40 feet. The number of trips between work centers is given in the following table: Figure 1. Interstation Activity Mix Trips between...
I input all the choices to give an idea of what they're asking and have no idea if they are correct. 9. Application: Elasticity and hotel rooms The following graph input tool shows the daily demand for hotel rooms at the Peacock Hotel and Casino in Las Vegas, Nevada. To help the hotel management better understand the market, an economist identified three primary factors that affect the demand for rooms each night. These demand factors, along with the values corresponding...
Explain please 2. Assume that the waveform shown at 100 90 the left represents the natural response of particular filter. For this waveform a) Determine the expression for the voltage, v(t). Your answer should have 80 a 70 60 50 40 30 the form v(t)Ve sin (wt). -at 20 10 b) Determine the resonant frequency, a. 0- -10 c) Plot the pole-zero diagram d) Determine the Q of this system. Does your answer agree with the length of the transient...
You did not receive full credit for this que Suppose you have the information shown in the table below about the quantity of a good supplied and demanded at various prices Price (S) Quantity demanded Quantity supplied 180 50 40 30 20 140 100 60 20 40 20 10 60 80 a. Draw the demand and supply curves from the data provided. Instructions: Use the tools provided (D1 and S1) to plot the demand curve (5 points total) and the...
Create a web page like the one shown here. The user can enter a number n, and when the button is clicked, the Harshad numbers between 1 and n are displayed: linking an html file with a javascript file. Count 'em! Find and Count the Niven Numbers Between 1 and: 200 Number of Nivens: 59 Niven Numbers: 1 23456789 10 12 18 20 21 24 27 30 36 40 42 45 48 50 54 60 63 70 72 80 81...
need help answering these with workout shown please 5-Star Lux Hotel Hotel Configuration Total Bed 1 Bed 2 Bed 3 (Single) (Double) (Penthouse) 30 60 20 1 1 area per room (square metres) number of rooms first floor - 240 square metre second floor - 240 square metre third floor - 240 square metre number of rooms floor space square metres) planned occupancy rate (%) (open 365 days) average selling price (Stroom/night) 1 3 4 3 4 3 4 9...