Suppose a Lean work center is being operated with a container size of 25 units and a demand rate of 100 units per hour. Also
0 0
Add a comment Improve this question Transcribed image text
Answer #1

solution :

given data  

n =25

μ = 100 per hour

μl = 180 min = 3 hours

r = 5 = 0.05

this is a lean work center so we use the ' Kanban ' formula to solve the problem

* n . k ≥  μl . μd .( 1+r )................. 1

Here  

no of containers = k

kanban container size = n

average lead time for repienshiment = μl

average demand rate = μd

safter facror = r

Now put the values in above formule and calculate

K  ≥ 100 * 3 ( 1+ 0.05 ) / 25

K ≥   100 * 3 ( 1.05 ) / 25

K ≥   315 / 25

K ≥   12.6

hence option " c " is correct

  

** please give an upvote ** thanking you  

Add a comment
Know the answer?
Add Answer to:
Suppose a Lean work center is being operated with a container size of 25 units and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area,...

    Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area, the demand is 100 parts per eight-hour day. It uses a container that holds eight parts. It typically takes about six hours to round-trip a container from one work center to the next and back again. It also desires to hold 15% safety stock of this part in the system. If it reduced the number of containers by one, how would this impact the...

  • Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly...

    Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system. Based on the required safety stock of zero and the number of...

  • Case 1:  The kanban system Suppose demand at the receiving work center B is 4...

    Case 1:  The kanban system Suppose demand at the receiving work center B is 4 parts per minute and a standard container holds 50 parts. Also assume that it takes 200 minutes of lead time for a container to make a complete circuit from work center A to work center B and back to A again, including all setup, run, move, and wait time. Question: Find n the number of containers needed in this case.

  • A work center is operated in an 8-hour shift to make 2.000 units. The allowance for...

    A work center is operated in an 8-hour shift to make 2.000 units. The allowance for the shift is 10%. Historica"y this work centers emciency has been 90%. What is the takt time (minuteunity? Select one: O A. 0.201 B. 0.174 ○ C. 0.144 ○ D, 0216 OE. None of them

  • Using the reorder level-order quantity model, and assuming a safety stock of 800, what is the...

    Using the reorder level-order quantity model, and assuming a safety stock of 800, what is the re-order point (R) given a daily demand of 300 units, a lead time of 5 days? 300 800 1500 2300 1100 Which of the following basic types of process structures needs to keep inventory of work-in-process component parts? Assemble to Order Make to Stock O None of the above Make to Order Engineer to Order Suppose a call center has one agent answering the...

  • Chapter overview 1. Reasons for international trade Resources reasons Economic reasons Other reasons 2. Difference between...

    Chapter overview 1. Reasons for international trade Resources reasons Economic reasons Other reasons 2. Difference between international trade and domestic trade More complex context More difficult and risky Higher management skills required 3. Basic concept s relating to international trade Visible trade & invisible trade Favorable trade & unfavorable trade General trade system & special trade system Volume of international trade & quantum of international trade Commodity composition of international trade Geographical composition of international trade Degree / ratio of...

  • 10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated...

    10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...

  • CASE 1-5 Financial Statement Ratio Computation Refer to Campbell Soup Company's financial Campbell Soup statements in...

    CASE 1-5 Financial Statement Ratio Computation Refer to Campbell Soup Company's financial Campbell Soup statements in Appendix A. Required: Compute the following ratios for Year 11. Liquidity ratios: Asset utilization ratios:* a. Current ratio n. Cash turnover b. Acid-test ratio 0. Accounts receivable turnover c. Days to sell inventory p. Inventory turnover d. Collection period 4. Working capital turnover Capital structure and solvency ratios: 1. Fixed assets turnover e. Total debt to total equity s. Total assets turnover f. Long-term...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT