Question

Question 4 (20 marks) (a) State the main three objects for fault analysis. (6 marks) (b) Explain why it is necessary to remov
0 0
Add a comment Improve this question Transcribed image text
Answer #1

- the system during the fault. of the required Circuit breakers. Selection of appropriate Schemes of protective relay unbalanPAC - Nok 2 *3121= R + x 40 x1000 (0.8) + + 8 4,975.19 Amp ii) RMS momentary Current at T= 0.5 Cycles : K(C) (-41777(XIR) 11) Current rating (e) Specification factors of fuse :- of the fuse 2) Breaking capacity or interrupting Capacity 3) Ambient t

Add a comment
Know the answer?
Add Answer to:
Question 4 (20 marks) (a) State the main three objects for fault analysis. (6 marks) (b)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Zone 1 Zone 3 Zone 2 Xice j1002 BE SO MW 0.8 pf lagging Vload =...

    Zone 1 Zone 3 Zone 2 Xice j1002 BE SO MW 0.8 pf lagging Vload = 30 kV Ti 50 MVA 11/132 kV X= 10% Tz 50 MVA 132/33 kV X=12% Figure 1 2. A 500 MVA, 20 kV, 50 Hz synchronous generator with reactances Xd" = 0.15, Xá = 0.24, Xo = 1.1 p.u. and time constant To = 0.035, Tó' = 2.0, TA = 0.2 seconds is connected to a circuit breaker. The generator is operating at 5%...

  • 1. A three-phase synchronous generator connected to a 345-KV transmission line through a transformer as shown...

    1. A three-phase synchronous generator connected to a 345-KV transmission line through a transformer as shown in Figure P1. Parameters of both generator and transformer are given in the figure. Transformer losses and exciting current are neglected. A three-phase short-circuit occurs on the line side of the circuit breaker when the generator is operated at rated terminal voltage and at no-load. The breaker interrupts the fault three cycles after fault inception. Neglect the effect of the transformer on the time...

  • Part B (20 marks) Figure 2 shows a three phase 22kV, 50Hz radial system, which is to be protected by two inverse- time...

    Part B (20 marks) Figure 2 shows a three phase 22kV, 50Hz radial system, which is to be protected by two inverse- time over-current relays B1 and B2. The maximum loads for this system are L 6 MVA, and L2- 5 MVA. The maximum fault currents at bus 1 and bus 2 are 1500A and 1000A respectively. The minimum fault currents at bus 1 and bus 2 are 900A and 650A respectively The line currents are measured using current transformers...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT