Journal entries.

Date Accounts Debit Credit
Dec 31 Wages expense $ 1,575
To wages payable $ 1,575
( accruing wages expense of one day for 7 employees)

Wages for one day for 7 employees = 7 x 225

Wages for one day for 7 employees = $ 1,575.

The payment is made on January 4 of next year. But on January 1, it is holiday and so no payment to be made. So Wednesday, Thursday and Fridays expense to be recognized as expense in new year.

Date Accounts Debit Credit
Jan 4 Wages expense $ 4,725
Wages payable $ 1,575
To Cash $ 6,300
( payment of wages)

3 days wages = 225 x 3 x 7

3 days Wages = 4,725.

SUMMARY:

On payment date, a total of 4 days payment is made but 3 days expense to be recognized in new year and one day expense in last year.

Add a comment
Know the answer?
Add Answer to:
Exercise 3-2 Adjusting and paying accrued wages LO P3 Pablo Management has seven employees, each of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 3-2 Adjusting and paying accrued wages LO P3 Pablo Management has five employees, each of...

    Exercise 3-2 Adjusting and paying accrued wages LO P3 Pablo Management has five employees, each of whom earns $250 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the five employees worked Monday, December 31, and Wednesday through Friday, January 2, 3, and 4. New Year's Day (January 1) was an unpaid holiday. Prepare the year-end adjusting entry for wages expense and record payment of the employees' wages on Friday,...

  • Exercise 3-3 Adjusting and paying accrued wages LO P3

    Exercise 3-3 Adjusting and paying accrued wages LO P3Pablo Management has ten employees, each of whom earns $195 per day. They are normally paid on Fridays for work completed. Monday through Friday of the same week. Near year-end, the ten employees worked Monday, December 31, and Wednesday through Friday, January 2.3, and 4 . New Year's Day (January 1) was an unpaid holiday.Prepare the year-end adjusting entry for wages expense and record payment of the employees' wages on Friday, January...

  • Exercise 3-1 Adjusting and paying accrued wages LO P1 Pablo Management has six part-time employees, each...

    Exercise 3-1 Adjusting and paying accrued wages LO P1 Pablo Management has six part-time employees, each of whom earns $185 per day They are paid on Fridays for work completed Monday through Friday of the same week. Near year Friday, January 2, 3, and 4. New Year's Day. (January 1) was an unpaid holiday end, the six employees worked Monday, December 31, and Wednesday through 1. Prepare the year-end adjusting entry for wages expenses 2. Prepare the journal entry to...

  • Exercise 3-1 Adjusting and paying accrued wages LO P1 Pablo Management has five part-time employees, each...

    Exercise 3-1 Adjusting and paying accrued wages LO P1 Pablo Management has five part-time employees, each of whom earns $105 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the five employees worked Monday, December 31, and Wednesday through Friday, January 2, 3, and 4. New Year's Day. (January 1) was an unpaid holiday 26 1. Prepare the year-end adjusting entry for wages expenses 2. Prepare the journal entry to...

  • Pablo Management has seven part-time employees, each of whom earns $125 per day. They are paid...

    Pablo Management has seven part-time employees, each of whom earns $125 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the seven employees worked Monday, December 31, and Wednesday through Friday, January 2, 3, and 4. New Year's Day. (January 1) was an unpaid holiday. 1. Prepare the year-end adjusting entry for wages expenses. 2. Prepare the journal entry to record payment of the employees' wages on Friday, January 4th.

  • Pablo Management has two employees, each of whom earns $130 per day. They are paid on...

    Pablo Management has two employees, each of whom earns $130 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the two employees worked Monday, December 31, and Wednesday through Friday. January 23, and 4. New Year's Day (January 1) was an unpaid holiday. Prepare the year-end adjusting entry for wages expense and record payment of the employees' wages on Friday, January 4. View transaction list Journal entry worksheet Alta Record...

  • Pablo Management has five employees, each of whom earns $150 per day. They are paid on...

    Pablo Management has five employees, each of whom earns $150 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the five employees worked Monday, December 31, and Wednesday through Friday, January 2, 3, and 4. New Year's Day (January 1) was an unpaid holiday. Prepare the year-end adjusting entry for wages expense and record payment of the employees' wages on Friday, January 4. View transaction list View journal entry worksheet...

  • Pablo Management has two employees, each of whom earns $220 per day. They are paid on...

    Pablo Management has two employees, each of whom earns $220 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the two employees worked Monday, December 31, and Wednesday through Friday, January 2, 3, and 4. New Year’s Day (January 1) was an unpaid holiday. Prepare the year-end adjusting entry for wages expense qnd record payment of the employees’ wages on Friday, January 4. Pablo Management has two employees, each of...

  • Pablo Management has five part-time employees, each of whom earns $250 per day.

    Pablo Management has five part-time employees, each of whom earns $250 per day. They are paid on Fridays for work completed Monday through Friday of the same week Near year-end, the five employees worked Monday, December 31, and Wednesday through Friday, January 2, 3, and 4. New Year's Day (January 1) was an unpaid holiday. 1. Prepare the year-end adjusting entry for wages expenses. 2. Prepare the journal entry to record payment of the employees' wages on Friday, January 4.

  • Pablo Management has five employees, each of whom earns $250 per day. They are paid on...

    Pablo Management has five employees, each of whom earns $250 per day. They are paid on Fridays for work completed Monday through Friday of the same week. Near year-end, the five employees worked Monday, December 31, and Wednesday through Friday. January 2, 3, and 4. New Year's Day (January 1) was an unpaid holiday. Prepare the year-end adjusting entry for wages expense and record payment of the employees' wages on Friday, January 4. View transaction list Journal entry worksheet <...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT