1. What was the company’s plantwide predetermined overhead rate?
(Round your answer to 2 decimal places.)
2. How much manufacturing overhead was applied to Job P and how
much was applied to Job Q? (Do not round intermediate
calculations.)
3. What was the total manufacturing cost assigned to Job P?
(Do not round intermediate calculations.)
4. If Job P included 20 units, what was its unit product cost?
(Do not round intermediate calculations.
Round your final answer to nearest whole dollar.)
5. What was the total manufacturing cost assigned to Job Q?
(Do not round intermediate calculations.)
6. If Job Q included 30 units, what was its unit product cost?
(Do not round intermediate calculations.
Round your final answer to nearest whole dollar.)
8. What was Sweeten Company’s cost of goods sold for March?
(Do not round intermediate calculations.)
Based on the information available in the question, we can answer as follows:-
Requirement 1:-
Step 1 :- Fixed overhead rate
=$25,000/4,000 hours
=$6.25 per hour
Step 2:- Variable overhead rate
=(2,500 * $1.4) + (1,500 * 2.20)
=$6,800/4,000 hours
=$1.7 per hour
Step 3:- Predetermined Overhead rate
=$6.25 + $1.7
Predetermined Overhead rate = $7.95 per hour
Requirement 2:-
Manufacturing overhead applied to P:-
2,300 hours * $7.95 per hour = $18,285
Manufacturing overhead applied to Q:-
1,700 hours * $7.95 per hour = $13,515
Requirement 3:-
Manufacturing cost assigned to P:-
Particulars | Amount |
Direct Materials | 13,000 |
Direct Labor | 21,000 |
Overheads | 18,285 |
Total | 52,285 |
Requirement 4:-
If P included 20 units, unit product cost is :- $52,285/20 units
Unit Product Cost = $2,614.25
Unit Product cost = $2,614(Rounded)
Kindly note that i have answered the first 4 questions per the HOMEWORKLIB RULESs. Request you to post the remaining questions separately so that we can answer them as well. All the best and please let me know if you have any questions via comments :)
1. What was the company’s plantwide predetermined overhead rate? (Round your answer to 2 decimal places.)...
1. What was the company’s plantwide predetermined overhead rate? (Round your answer to 2 decimal places.) 2. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.) 4. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole...
1. What was the company’s plantwide predetermined overhead rate? (Round your answer to 2 decimal places.) 2. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.) 4. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole...
PLEASE SHOW WORK!! QUESTIONS: 1. What was the company’s plantwide predetermined overhead rate? (Round your answer to 2 decimal places.) 2. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.) 4. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final...
1. What was the company’s plantwide predetermined overhead rate? 1a. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) b. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.) 2a. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole dollar.) 2b. What was the total manufacturing...
1.What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 2.How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 4. What was the total...
Questions: 1. What was the company’s plantwide predetermined overhead rate? 2. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? 3. What was the total manufacturing cost assigned to Job P? 4. If Job P included 20 units, what was its unit product cost? 5. What was the total manufacturing cost assigned to Job Q? 6. If Job Q included 30 units, what was its unit product cost? 7. Assume that Sweeten...
1. what was the companys plantwide predetermined overhead rate? 2.How much manufacturing overhead was applied to Job P and how much was applied to Job Q? 3.What was the total manufacturing cost assigned to Job P? 4.If Job P included 20 units, what was its unit product cost? 5.What was the total manufacturing cost assigned to Job Q? 6. If Job Q included 30 units, what was its unit product cost? 7. 8. what was Sweeten Companys cost of goods...
1. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 2. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 3. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 4. What was...
9. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.) 10. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 11. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 12. If Job...