Question

Ray Company provided the following excerpts from its Production Departments flexible budget performance report. (Round rate

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Production Department Flexible budget performance report

For the month ended August 31

Actual results Spending variance Flexible budget Activity variance Planning budget
Labor hour 9500 9500 9020
Direct labor 15 145530 3030 U 142500 7200 U 135300
Indirect labor 7440 + 1.10q 14586 3304 F 17890 528 U 17362
Utilities 6700 + 0.90q 16720 1470 U 15250 432 U 14818
Supplies 1614 + 0.30q 4968 504 U 4464 144 U 4320
Equipment Depreciation 78900 78900 0 None 78900 0 None 78900
Factory administration 18740 + 1.10q 28030 1160 F 29190 528 U 28662
Total expense 288734 540 U 288194 8832 U 279362
Add a comment
Know the answer?
Add Answer to:
Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (.e., zero variance). Input all amounts as positive values.) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 For the Month Actual Flexible Results Spending Variances variances Budget 9,600 Activity Variances Planning Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Planning Budget Actual Results Flexible Activity Variances Spending Variances Budget Labor-hours (q) 9,590 9,110 q)...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Spending Variances Results Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Spending Variances Results Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Spending Variances Results Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Flexible Results Spending Variances Budget 9,580 Activity Variances Planning Budget 9,100 Labor-hours (9) Direct labor...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Spending Variances Flexible Results Spending Variances Budget 9,520 Activity Variances Planning Budget 9,040 Labor-hours...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour answers to 2 decimal places. Indicate the effect of each varlance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (I.e., zero varlance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget 9,520 9,520 Activity Variances Planning Budget 9,040 Labor-hours (9)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT