During 2020 the Tonka Corp. began construction for which it will invoice a total of $ 600,000. The project ended on December 15, 2021. Additional information related to this project is presented below: 2020 2021 Costs incurred in the period $ 225,000 $ 255,000 Estimated costs to complete the project 225,000 -0- Customer billing 240,000 360,000 Cash Received from Clients 200,000 400,000 Assuming Tonka uses the CONTRACT COMPLETED method, what will be the gross profit reported in the 2020 Statement of Income and Expenses related to this project?
Select one: a. $ 75,000 b. $ 345,000 c. $ 0 d. $ 120,000
Tonka uses the CONTRACT COMPLETED method, the gross profit will be reported in the 2020 Statement of Income and Expenses related to this project will be $ 0 because under completed contract method, Revenue is recognized in the year of completion only & gross profit will be reported at the same time. |
Correct answer is option C . |
During 2020 the Tonka Corp. began construction for which it will invoice a total of $...
Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...
Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...
Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000. Short recognizes revenue over time according to percentage of completion method. The balance sheet shows the following accounts at the end of 2021: A/R of $40,000, Construction in Progress of $200,000, Less: Billings on Construction Contract of $170,000. The income statement shows Income on the contract of $30,000 at the end of 2021. What was the total estimated cost of the project at the...
Cady Construction received a contract to construct a hospital for $2,500,000. Construction began in 2019 and ended in 2020. Cost and other data are presented below: 2019 2020 Costs incurred during the year $1,500,000 $1,300,000 Estimated costs to complete 1,200,000 0 Billings during the year 1,200,000 1,300,000 Cash collections during the year 1,000,000 1,500,000 What is gross profit recognized during 2020 if Cady recognizes revenue over time according to percentage of completion? a. $100,000 b. $200,000 c. ($200,000) d. $0...
Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...