Teal, Inc. began work on a $6,550,000 contract in 2020 to
construct an office building. During 2020, Teal, Inc. incurred
costs of $1,817,440, billed its customers for $1,316,000, and
collected $1,039,000. At December 31, 2020, the estimated
additional costs to complete the project total $3,094,560.
Prepare Teal’s 2020 journal entries using the
percentage-of-completion method.
Answer
Date |
Accounts title |
Debit |
Credit |
2020 |
Construction in Progress |
$1,817,440 |
|
Various accounts |
$1,817,440 |
||
(construction cost incurred) |
|||
2020 |
Accounts receivables |
$1,316,000 |
|
Billing on Construction contracts |
$1,316,000 |
||
(amount billed during the year) |
|||
2020 |
Cash |
$1,039,000 |
|
Accounts receivables |
$1,039,000 |
||
(cash received) |
|||
2020 |
Construction in Progress |
$606,060 |
|
Cost of construction |
$1,817,440 |
||
Revenue from Long Term contract |
$2,423,500 |
||
(revenue recognised) |
--Working
Working |
2020 |
|
A |
Contract Price |
$6,550,000 |
B |
Cost Incurred to Date |
$1,817,440 |
C |
Estimated cost yet to be incurred to complete the contract |
$3,094,560 |
D = B+C |
Total Cost |
$4,912,000 |
E = (B/D) x 100 |
% of Completion |
37.00% |
F = A x E |
Revenue to date |
$2,423,500 |
G |
Revenue of Previous year |
$0 |
H = F - G |
Net Revenue this year |
$2,423,500 |
I (=B) |
Cost to date |
$1,817,440 |
J |
Cost to date of previous year |
$0 |
K = I - J |
Net Cost for the year |
$1,817,440 |
L = H - K |
Gross Profits |
$606,060 |
Teal, Inc. began work on a $6,550,000 contract in 2020 to construct an office building. During...
Sarasota, Inc. began work on a $6,339,000 contract in 2020 to
construct an office building. During 2020, Sarasota, Inc. incurred
costs of $1,537,470, billed its customers for $1,141,000, and
collected $961,000. At December 31, 2020, the estimated additional
costs to complete the project total $3,121,530.
Prepare Sarasota’s 2020 journal entries using the
percentage-of-completion method.
Sarasota, Inc. began work on a $6,339,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,537,470, billed its customers...
Bridgeport, Inc. began work on a $7,043,000 contract in 2020 to construct an office building. During 2020, Bridgeport, Inc. incurred costs of $1.891,800, billed its customers for $1,315,000, and collected $939,000. At December 31, 2020. the estimated additional costs to complete the project total $3,363.200. Prepare Bridgeport's 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...
Cheyenne Construction Company began work on a $424,000
construction contract in 2020. During 2020, Cheyenne incurred costs
of $279,500, billed its customer for $204,500, and collected
$170,500. At December 31, 2020, the estimated additional costs to
complete the project total $150,500.
Prepare Cheyenne’s journal entry to record profit or loss, if any,
using (a) the percentage-of-completion method and (b) the
completed-contract method.
Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...
Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
adland, Inc. began work on a $7,215,000
contract in 2020 to construct an office building. Headland uses the
completed-contract method. At December 31, 2020, the balances in
certain accounts were Construction in Process $1,813,000, Accounts
Receivable $261,000, and Billings on Construction in Process
$1,001,000. Indicate how these accounts would be reported in
Headland’s December 31, 2020, balance sheet.
Headland, Inc. began work on a $7,215,000 contract in 2020 to construct an office building. Headland uses the completed-contract method. At December...
Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...