Total direct labor hours=($110/11 per labor hour)=10 hours
Hence total overhead=10 hours*$20 per hour
=$200
a.Total manufacturing cost=Direct materials+Direct labor+Total overhead
=270+110+200=$580
b.Unit product cost=580/70
=$8.29 per unit(Approx)
Mickley Company's plantwide predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage...
Mickley Company's plantwide predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: $ 270 $ 225 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost Unit product cost 2....
Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500 Direct materials Direct labor $ 210 $ 110 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost...
Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 250 $ 55 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 70 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost...
Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 165 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 70 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) Total manufacturing cost 2. Unit product cost per...
Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 230 $ 110 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost...
Mickley Company's plantwide predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: $ 290 $ 225 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 70 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost Unit product cost 2....
Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 230 $ 110 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) x Answer is complete but not entirely correct....
Mickley Company's plantwide predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: Direct materials $ 270 Direct labor $ 70 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 30 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.)
Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following Information pertains to Job A-500: Direct materials $290 Direct labor $ 220 Requlrecd 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 declmal places.) 1. Total manufacturing cost 2. Unit product cost per...
Mickley Company’s plantwide predetermined overhead rate is $20.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: Direct materials $ 240 Direct labor $ 150 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.)