Question

Cinder Company had the following department information for the month: Total materials cost: $60,000 Equivalent units...

Cinder Company had the following department information for the month:
Total materials cost: $60,000
Equivalent units of materials: $10,000
Total conversion costs: $90,000
Equivalent units of conversion costs: $20,000

How much is the total manufacturing cost per unit? Show work.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Material cost per unit = 60000/10000 = 6

Conversion cost per unit = 90000/20000 = 4.5

Total manufacturing cost per unit = 6+4.5 =10.5 per unit

Add a comment
Know the answer?
Add Answer to:
Cinder Company had the following department information for the month: Total materials cost: $60,000 Equivalent units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Current Attempt in Progress Bramble Company had the following department information for the month: Total materials...

    Current Attempt in Progress Bramble Company had the following department information for the month: Total materials costs $ 53000 Equivalent units of materials Total conversion costs Equivalent units of conversion costs 10000 $95000 19000 How much is the total manufacturing cost per unit? $5.30. $10.30 $5.00 $5.53 Save for Later Attemp

  • Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for...

    Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs — 3,500   Equivalent units of...

  • Multiple Choice Question 116 Marigold Company had the following department Information for the month: Total materials...

    Multiple Choice Question 116 Marigold Company had the following department Information for the month: Total materials costs Equivalent units of materials Total conversion costs Equivalent units of conversion costs $52000 10000 $77000 25000 What is the total manufacturing cost per unit? $8.28. $3.69 O $5.20. 0 $3.08.

  • Question 34 Fullerton Company has the following equivalent units for October: materials 40,000 and conversion costs...

    Question 34 Fullerton Company has the following equivalent units for October: materials 40,000 and conversion costs 15,000. Production cost data are: Materials Conversion Work in process, October 1 $ 50,000 $ 7.500 Costs added in October 130.000 22,500 The unit production costs for October are: $3.25 Materials Cost per unit and $1.50 Conversion Costs per unit $4.50 Materials Cost per unit and $2.00 Conversion Costs per unit $3.25 Materials Cost per unit and $.50 Conversion Costs per unit 01.25 Materials...

  • Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,000 tons in...

    Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,000 tons in beginning work in process inventory (60% complete) on October 1. During October, 50,800 tons were completed. The ending work in process inventory on October 31 was 2,500 tons (50% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? units Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs —...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs —...

  • Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the...

    Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 46,000 46,000 Add: Units in ending work in process ×      Percentage complete:         10,000 × 100% direct materials 10,000 —         10,000 × 40% conversion materials — 4,000 Eqivalent units of output 56,000 50,000 Costs:         Work in process, December 1:           Direct materials $66,000           Conversion costs 11,000           Total...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 5,000 × 0% direct materials — 5,000 × 50% conversion Costs 2,500 Add: Units in ending work in process × Percentage complete: 12,000 × 100% direct materials 12,000 — 12,000 × 35% conversion Costs — 4,200...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 5,000 × 0% direct materials — 5,000 × 50% conversion Costs 2,500 Add: Units in ending work in process × Percentage complete: 12,000 × 100% direct materials 12,000 — 12,000 × 35% conversion Costs — 4,200...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT