Required information The Hard Rock Mining Company is developing cost formulas for management planning and decision-making pur
quares Regression Saved Required information 4. To remove a point from the graph, click on the point and select delete option
een na ! Required information $20.000 Year 22nd quarter $0 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Year 23rd quarter D
0 0
Add a comment Improve this question Transcribed image text
Answer #1

(1)

Quarter Direct labour hours Utilities cost
Y1 Q1                5,800 $          58,000
Y1 Q2                3,800 $          53,000
Y1 Q3                4,800 $          68,000
Y1 Q4                6,800 $          83,000
Y2 Q1              10,800 $        108,000
Y2 Q2                9,800 $        113,000
Y2 Q3                8,800 $          93,000
Y2 Q4              11,800 $        128,000

$140,000 $120,000 $100,000 $80,000 $60,000 Utilities cost $40,000 $20,000 2,000 4,000 6,000 8,000 10,000 12,000 14,000

(2) Regression equation required , y = 17800 + 9x

Working:

Regression equation, y = a+bx

Variable cost = b and

5 = ηΣxy - (Σκ)(Σy) ηΣx - (Σx)

Fixed cost = a

Σy - ΕΣx n

Quarter Direct labour hours (x) Utilities cost(y) X^2 xy
Y1 Q1                5,800 $          58,000      33,640,000 $      336,400,000
Y1 Q2                3,800 $          53,000      14,440,000 $      201,400,000
Y1 Q3                4,800 $          68,000      23,040,000 $      326,400,000
Y1 Q4                6,800 $          83,000      46,240,000 $      564,400,000
Y2 Q1              10,800 $        108,000    116,640,000 $ 1,166,400,000
Y2 Q2                9,800 $        113,000      96,040,000 $ 1,107,400,000
Y2 Q3                8,800 $          93,000      77,440,000 $      818,400,000
Y2 Q4              11,800 $        128,000    139,240,000 $ 1,510,400,000
Total              62,400 $        704,000    546,720,000 $ 6,031,200,000

By substituting the values in the equations,

Variable cost = $9

Fixed cost = $17,800

Add a comment
Know the answer?
Add Answer to:
Required information The Hard Rock Mining Company is developing cost formulas for management planning and decision-making...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The...

    The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The company's cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst has decided to...

  • The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The...

    The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The company's cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst has decided to...

  • The Hard Rock Mining Company is developing cost formulas for management planning and decision-mak...

    The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The company’s cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base with which the cost might be closely correlated. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst...

  • ment Help Save & E Che The Hard Rock Mining Company is developing cost formulas for...

    ment Help Save & E Che The Hard Rock Mining Company is developing cost formulas for management planning and decision making purposes. The company's cost analyst has concluded that utlities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better...

  • Saved Help Save 6A Assignment The following information applies to the questions displayed below.] The Hard...

    Saved Help Save 6A Assignment The following information applies to the questions displayed below.] The Hard Rock Mining Company is developing cost formulas for management planning and decision- making purposes. The company's cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to thinks that direct labor-hours would be a better base. The cost...

  • The Hard Rock Mining Company is trying to develop cost formula for utility cost.Two independent variables...

    The Hard Rock Mining Company is trying to develop cost formula for utility cost.Two independent variables are being considered: Tons Mined and Direct Labor hours. As the managerial accountant, you are to decide which independent variable is best to use. Each question is worth 2 points. The following quarterly information is available for Tons Mined: Quarter Tons Mined Utility Cost Year 1--First 15,000 $50,000 Year 1--Second 11,000 $45,000 Year 1--Third 21,000 $60,000 Year 1--Fourth 12,000 $75,000 Year 2--First 18,000 $100,000...

  • The Hard Rock Mining Company is trying to develop cost formula for utility cost.Two independent variables...

    The Hard Rock Mining Company is trying to develop cost formula for utility cost.Two independent variables are being considered: Tons Mined and Direct Labor hours. As the managerial accountant, you are to decide which independent variable is best to use. Each question is worth 2 points. The following quarterly information is available for Tons Mined: Quarter Tons Mined Utility Cost Year 1--First           15,000 $      50,000 Year 1--Second           11,000 $      45,000 Year 1--Third           21,000 $      60,000 Year 1--Fourth...

  • The following quarterly information is available for Tons Mined Quarter Tons Mined Utility Cost Year 1-First 15,000 50,000 Year 1-Second 11,000 45,000 Year 1--Third 21,000 60,000 Year 1--Fourth 12,...

    The following quarterly information is available for Tons Mined Quarter Tons Mined Utility Cost Year 1-First 15,000 50,000 Year 1-Second 11,000 45,000 Year 1--Third 21,000 60,000 Year 1--Fourth 12,000 75,000 Year 2-First 18,000 100,000 Year 2-Second 25,000 105,000 Year 2--Third 30,000 $85,000 Year 2--Fourth 28,000 120,000 The following quarterly information is available for Direct Labor Hours Quarter DLH's Utility Cost Year 1-First 5,000 50,000 Year 1-Second 3,000 S 45,000 Year 1--Third 4,000 $ 60,000 Year 1--Fourth 6,000 75,000 Year 2-First...

  • The direct labor budget of Yuvwell Corporation for the upcoming fiscal year contains the following details concerni...

    The direct labor budget of Yuvwell Corporation for the upcoming fiscal year contains the following details concerning budgeted direct labor-hours: Budgeted direct labor-hours 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 10,600 9.500 9,800 10,600 The company uses direct labor-hours as its overhead allocation base. The variable portion of its predetermined manufacturing overhead rate is $5.25 per direct labor-hour and its total fixed manufacturing overhead is $74,000 per quarter. The only noncash item included in fixed manufacturing overhead is depreciation,...

  • Four grams of musk oil are required for each bottle of Mink Caress, a very popular...

    Four grams of musk oil are required for each bottle of Mink Caress, a very popular perfume made by a small company in western Siberia. The cost of the musk oil is $2.10 per gram. Budgeted production of Mink Caress is given below by quarters for Year 2 and f the first quarter of Year 3: Year 2 Second Third 128,000 188,000 First 98,000 Budgeted production, in bottles Year 3 First 108,000 Fourth 138,000 Musk oil has become so popular...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT