Question

Q3. (25 marks)Lower BoundExpected ValueUpper BoundSales quantity Sales price per unit Variable cost per unit Fixed...

Q3. (25 marks)Lower BoundExpected ValueUpper BoundSales quantity Sales price per unit Variable cost per unit Fixed cost95001000010500$9.75$10.00$10.25$4.80$5.20$5.60$15,000.00$18,000.00$21,000.00Initial requirement for equipment: S120,000 Depreciation: Straight-line to zero over the four-year life of the project with no salvage value. Required rate of return: 15% Marginal tax rate: 35%Calculate NPV according to best case scenario.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Best case scenario will be when:

Sales quantity is at upper bound = 10,500 units

Sales price per unit is at upper bound = $10.25

Variable cost per unit is at lower bound = $4.80

Fixed cost is at lower bound = $15,000

Initial investment = $120,000

Annual depreciation = 120000 / 4 = $30,000

Annual Cash flows = ((Sales price - Variable cost per unit)* sales quantity - Fixed cost) * (1 - tax rate) + Depreciation * Tax rate

= ((10.25 - 4.80)* 10500 - 15000) *(1- 35%) + 30000 * 35%

= $37946.25

Best case NPV = Annual cash flow * PV factor for annuity - Initial Investment

= 37946.25 *((1 - 1 /(1+15%)^4)/15%) - 120000

= -11664.28

NPV according to best case scenario = -$11,664.28 or ($11,664.28)

Add a comment
Know the answer?
Add Answer to:
Q3. (25 marks)Lower BoundExpected ValueUpper BoundSales quantity Sales price per unit Variable cost per unit Fixed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Magellen Industries is analyzing a new project. The data they have gathered to date is as...

    Magellen Industries is analyzing a new project. The data they have gathered to date is as follows: Lower Bound Expected Value Upper Bound Sales quantity 9500 10000 10500 Sales price per unit $9.75 $10.00 $10.25 Variable cost per unit $4.80 $5.20 $5.60 Fixed cost $15,000.00 $18,000.00 $21,000.00 Initial requirement for equipment: $120,000 Depreciation: Straight-line to zero over the four-year life of the project with no salvage value. Required rate of return: 15% Marginal tax rate: 35% What is the operating...

  • Variable cost: 20 Fixed cost: 350,000 Unit Price:40 Expected sales: 34,000 units per year However, you...

    Variable cost: 20 Fixed cost: 350,000 Unit Price:40 Expected sales: 34,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is...

  • Q3. (25 marks) A project requires an initial fixed asset investment of $600,000, which will be...

    Q3. (25 marks) A project requires an initial fixed asset investment of $600,000, which will be depreciated straight-line to zero over the six-year life of the project. The pre-tax salvage value of the fixed assets at the end of the project is estimated to be $50,001. Projected sales volume for each year of the project is shown below. The sale price is $50 per unit for the first three years, and $45 per unit for years 4 through 1. A...

  • is ok for the fraction as well Q3. (25 marks) A project requires initial fixed asset...

    is ok for the fraction as well Q3. (25 marks) A project requires initial fixed asset investment of $600,000, which will be depreciated straight line to zero over the six year life of the project. The pre-tax salvage value of the fixed astets at the end of the project is estimated to be $50,001. Projected sales volume for each year of the project is shown below. The sale price is $50 per unit for the first three years, and $45...

  • Q3. (25 marks) A project requires an initial fixed asset investment of $600,000, which will be...

    Q3. (25 marks) A project requires an initial fixed asset investment of $600,000, which will be depreciated straight line to zero over the six-year life of the project. The pre-tax salvage value of the fixed assets at the end of the project is estimated to be $50,001. Projected sales volume for each year of the project is shown below. The sale price is $50 per unit for the first three years, and $45 per unit for years 4 through 1....

  • The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost:...

    The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 60 $ 40 $420,000 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost:...

    The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 80 $ 60 $460,000 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line...

  • The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable...

    The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the...

  • URGENTTT The most likely outcomes for a particular project are estimated as follows: Unit price: Variable...

    URGENTTT The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: 80 68 $280,eee 30,eee units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated straight-line over...

  • The most likely outcomes for a particular project are estimated as follows: points Unit price: Variable...

    The most likely outcomes for a particular project are estimated as follows: points Unit price: Variable cost: Fixed cost: Expected sales: $ 50 $ 30 $420,000 41,000 units per year ebook Print However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT