Q3. (25 marks)Lower BoundExpected ValueUpper BoundSales quantity Sales price per unit Variable cost per unit Fixed cost95001000010500$9.75$10.00$10.25$4.80$5.20$5.60$15,000.00$18,000.00$21,000.00Initial requirement for equipment: S120,000 Depreciation: Straight-line to zero over the four-year life of the project with no salvage value. Required rate of return: 15% Marginal tax rate: 35%Calculate NPV according to best case scenario.
Answer:
Best case scenario will be when:
Sales quantity is at upper bound = 10,500 units
Sales price per unit is at upper bound = $10.25
Variable cost per unit is at lower bound = $4.80
Fixed cost is at lower bound = $15,000
Initial investment = $120,000
Annual depreciation = 120000 / 4 = $30,000
Annual Cash flows = ((Sales price - Variable cost per unit)* sales quantity - Fixed cost) * (1 - tax rate) + Depreciation * Tax rate
= ((10.25 - 4.80)* 10500 - 15000) *(1- 35%) + 30000 * 35%
= $37946.25
Best case NPV = Annual cash flow * PV factor for annuity - Initial Investment
= 37946.25 *((1 - 1 /(1+15%)^4)/15%) - 120000
= -11664.28
NPV according to best case scenario = -$11,664.28 or ($11,664.28)
Q3. (25 marks)Lower BoundExpected ValueUpper BoundSales quantity Sales price per unit Variable cost per unit Fixed...
Magellen Industries is analyzing a new project. The data they have gathered to date is as follows: Lower Bound Expected Value Upper Bound Sales quantity 9500 10000 10500 Sales price per unit $9.75 $10.00 $10.25 Variable cost per unit $4.80 $5.20 $5.60 Fixed cost $15,000.00 $18,000.00 $21,000.00 Initial requirement for equipment: $120,000 Depreciation: Straight-line to zero over the four-year life of the project with no salvage value. Required rate of return: 15% Marginal tax rate: 35% What is the operating...
Variable cost: 20 Fixed cost: 350,000 Unit Price:40 Expected sales: 34,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is...
Q3. (25 marks) A project requires an initial fixed asset investment of $600,000, which will be depreciated straight-line to zero over the six-year life of the project. The pre-tax salvage value of the fixed assets at the end of the project is estimated to be $50,001. Projected sales volume for each year of the project is shown below. The sale price is $50 per unit for the first three years, and $45 per unit for years 4 through 1. A...
is ok for the fraction as well Q3. (25 marks) A project requires initial fixed asset investment of $600,000, which will be depreciated straight line to zero over the six year life of the project. The pre-tax salvage value of the fixed astets at the end of the project is estimated to be $50,001. Projected sales volume for each year of the project is shown below. The sale price is $50 per unit for the first three years, and $45...
Q3. (25 marks) A project requires an initial fixed asset investment of $600,000, which will be depreciated straight line to zero over the six-year life of the project. The pre-tax salvage value of the fixed assets at the end of the project is estimated to be $50,001. Projected sales volume for each year of the project is shown below. The sale price is $50 per unit for the first three years, and $45 per unit for years 4 through 1....
The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 60 $ 40 $420,000 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line...
The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 80 $ 60 $460,000 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line...
The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the...
URGENTTT The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: 80 68 $280,eee 30,eee units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated straight-line over...
The most likely outcomes for a particular project are estimated as follows: points Unit price: Variable cost: Fixed cost: Expected sales: $ 50 $ 30 $420,000 41,000 units per year ebook Print However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will...