a:
NPV | 2891846.32 |
Workings
Best case | |
Sales units | 45100 |
Price | 55 |
variable cost | 27 |
Fixed cost | 378000 |
Total sales | 2480500 |
Total cost | 1595700 |
Year |
Cost of new machine |
Tax
shield- depreciation |
(Sales-cost) after tax |
Net CF |
0 | -1200000 | -1200000 | ||
1 | 25200 | 698992 | 724192 | |
2 | 25200 | 698992 | 724192 | |
3 | 25200 | 698992 | 724192 | |
4 | 25200 | 698992 | 724192 | |
5 | 25200 | 698992 | 724192 | |
6 | 25200 | 698992 | 724192 | |
7 | 25200 | 698992 | 724192 | |
8 | 25200 | 698992 | 724192 | |
9 | 25200 | 698992 | 724192 | |
10 | 25200 | 698992 | 724192 |
b:
NPV | -1143316.96 |
Worst cae | |
Sales units | 36900 |
Price | 45 |
variable cost | 33 |
Fixed cost | 462000 |
Total sales | 1660500 |
Total cost | 1679700 |
Year |
Cost of new machine |
Tax
shield- depreciation |
(Sales-cost) after tax |
Net CF |
0 | -1200000 | -1200000 | ||
1 | 25200 | -15168 | 10032 | |
2 | 25200 | -15168 | 10032 | |
3 | 25200 | -15168 | 10032 | |
4 | 25200 | -15168 | 10032 | |
5 | 25200 | -15168 | 10032 | |
6 | 25200 | -15168 | 10032 | |
7 | 25200 | -15168 | 10032 | |
8 | 25200 | -15168 | 10032 | |
9 | 25200 | -15168 | 10032 | |
10 | 25200 | -15168 | 10032 | |
NPV | -1143316.96 |
The most likely outcomes for a particular project are estimated as follows: points Unit price: Variable...
The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 60 $ 40 $420,000 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line...
The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 80 $ 60 $460,000 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 250,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
URGENTTT The most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: 80 68 $280,eee 30,eee units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated straight-line over...
The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 380,000 Expected sales: 37,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.7 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1 million, which will be depreciated straight-line over the...
Problem 10-9 Scenarlo Analysls (LO3) The most likely outcomes for a particular project are estimated as follows: Unit price Variable cost: Fixed cost Expected sales: 58 30 $328,eee 31,808 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.5 million, which will...
Variable cost: 20 Fixed cost: 350,000 Unit Price:40 Expected sales: 34,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is...
You are considering a proposal to produce and market a new sluffing machine. The most likely outcomes for the project are as follows: Expected sales: 115,000 units per year Unit price: $220 Variable cost: $132 Fixed cost: $4,890,000 The project will last for 10 years and requires an initial investment of $16.70 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 30%, and the required rate of return...