Exercise 18-33 (Part Level Submission) During 2020, Novak Company started a construction job with a contract...

Exercise 18-33 (Part Level Submission)

During 2020, Novak Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$383,800 $807,380 $1,070,000

Estimated costs to complete

626,200 298,620 –0–

Billings to date

297,000 895,000 1,580,000

Collections to date

271,000 807,000 1,433,000

Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Account Titles and Explanation

Debit

Credit

(To record cost of construction.)

(To record progress billings.)

(To record collections.)

(To recognize revenue.)

List of Accounts:

Accounts Receivable
Accounts Payable
Advertising Expense
Allowance for Sales Returns and Allowances
Billings on Construction in Process
Cash
Commission Expense
Commission Revenue
Construction in Process
Construction Expenses
Cost of Goods Sold
Cost of Installment Sales
Deferred Gross Profit
Delivery Expense
Discount on Notes Receivable
Estimated Inventory Returns
Finished Goods Inventory
Franchise Revenue
Freight-Out
Gain on Repossession
Income Summary
Installment Accounts Receivable
Installment Sales Revenue
Interest Expense
Interest Revenue
Inventory
Inventory on Consignment
Liability to Enyart Company
License Revenue
Loss from Long-Term Contracts
Loss on Repossession
Materials, Cash, Payables
No Entry
Notes Receivable
Operating Expenses
Payable to Consignor
Purchases
Realized Gross Profit
Repossessed Merchandise
Retained Earnings
Returned Inventory
Revenue from Consignment Sales
Revenue from Franchise Fees
Revenue from Long-Term Contracts
Sales Discounts
Sales Discounts Forfeited
Sales Returns and Allowances
Sales Revenue
Service Revenue
Unearned Franchise Revenue
Unearned Sales Revenue
Unearned Service Revenue
Warranty Expense

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • Requirement asked: Journal entries 2021

Date

Accounts title

Debit

Credit

2021

Construction in Progress

$423,580

   Material, Cash Payables

$423,580

(construction cost incurred)

2021

Accounts receivables

$598,000

Billing on Construction in Process

$598,000

(amount billed during the year)

2021

Cash

$536,000

Accounts receivables

$536,000

(cash received)

2021

Construction in Progress

$129,420

Construction expense

$423,580

Revenue from Long Term contract

$553,000

(revenue recognised)

Add a comment
Know the answer?
Add Answer to:
Exercise 18-33 (Part Level Submission) During 2020, Novak Company started a construction job with a contract...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • Problem 18-05 (Part Level Submission) Pronghorn Ranch & Farm is a distributor of ranch and farm...

    Problem 18-05 (Part Level Submission) Pronghorn Ranch & Farm is a distributor of ranch and farm equipment. Its products range from small tools, power equipment for trench-digging and fencing, grain dryers, and barn winches. Most products are sold direct via its company catalog and Internet site. However, given some of its specialty products, select farm implement stores carry Pronghorn's products. Pricing and cost information on three of Pronghorn's most popular products are as follows. Item Mini-trencher Power fence hole auger...

  • Pharoah Company sells goods that cost $295,000 to Ricard Company for $446,000 on January 2, 2017....

    Pharoah Company sells goods that cost $295,000 to Ricard Company for $446,000 on January 2, 2017. The sales price includes an installation fee, which has a standalone selling price of $42,000. The standalone selling price of the goods is $404,000. The installation is considered a separate performance obligation and is expected to take 6 months to complete. (a) Prepare the journal entry (if any) to record the sale on January 2, 2017. (Credit account titles are automatically indented when amount...

  • On March 10, 2017, Sandhill Company sold to Barr Hardware 160 tool sets at a price...

    On March 10, 2017, Sandhill Company sold to Barr Hardware 160 tool sets at a price of $50 each (cost $30 per set) with terms of n/60, f.o.b. shipping point. Sandhill allows Barr to return any unused tool sets within 60 days of purchase. Sandhill estimates that (1) 10 sets will be returned, (2) the cost of recovering the products will be immaterial, and (3) the returned tools sets can be resold at a profit. On March 25, 2017, Barr...

  • On January 1, 2020, Ivanhoe Ltd. sold on account 1,200 units of its product for a...

    On January 1, 2020, Ivanhoe Ltd. sold on account 1,200 units of its product for a total price of $567,0000 and a cost of $489,000. The products have a one- year assurance-type warranty and Ivanhoe estimates that the cost will be $22,000. By the company's year-end December 31, 2020, actual warranty costs related to the products sold was $17,200, paid in cash. Prepare all appropriate journal entries including the sale of merchandise. (Credit account titles are automatically indented when the...

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...

  • During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job...

    During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT