Answer
Assembly |
Testing |
Total |
||
A |
Total Overhead cost |
$202,800 |
$780,000 |
$982,800 |
B |
Total machine hours |
3900 |
7800 |
11700 |
C = A/B |
Overhead rates |
$52 |
$100 |
$84 |
Commercial motor |
$126 |
[1.5 DMH x $ 84] |
Residential motor |
$252 |
[3.0 DMH x $ 84] |
Commercial motor |
$126 |
(0.5 hours x $52)+(1 hour x $100) |
Residential motor |
$252 |
(1 hours x $52)+(2 hour x $100) |
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Pineapple Motor...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Pineapple Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Pineapple: Assembly Department $240,000...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Pineapple Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Pineapple: Assembly Department $194,400...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Pineapple Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testling. Presently, the company uses a single plantwide factory overhead rate for allocating factory Overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Pineapple: Assembly Department $194,400...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Eclipse Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Eclipse: Assembly Department $280,000...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Eclipse Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Eclipse: Assembly Department $280,000...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Eclipse Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Eclipse: Assembly Department Testing...
Single Plantwide and Multiple Production Department Factory Overhead Rate Methods and Product Cost Distortion Eclipse Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Eclipse: Assembly Department $280,000...
TACT Ovementowo ProC. TOWEVESTICIS CONSIG rate method. The following factory overhead was budgeted for Pineapple: T IG Assembly Department Testing Department Total $155,400 599,400 $754,800 Direct machine hours were estimated as follows: 3,700 hours Assembly Department Testing Department 7,400 Total 11,100 hours In addition, the direct machine hours (dmh) used to produce a unit of each product in each department were determined from engineering records, as follows: Commercial 0.50 dmh Residential 1.00 dmh Assembly Department Testing Department 1.00 2.00 Total...
Pineapple Motor Company manufactures two types of specialty electric motors, a commercial motor and a residential motor, through two production departments, Assembly and Testing. Presently, the company uses a single plantwide factory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for Pineapple: Assembly Department $165,600 Testing Department 633,600 Total $799,200 Direct machine hours were estimated as follows: 3,600 hours...
Single Hantwed Production Department Factory Overhead Rathods and Product Cost Distortion Edise Motor Company manufactures two types of specialty electric motors, a commercial motor da residential motor, though two production departments, Assembly and in the company single plantwide actory overhead rate for allocating factory overhead to the two products. However, management is considering using the multiple production department factory overhead rate method. The following factory overhead was budgeted for de Assembly Department Testing Department Total 1280.000 100.000 $1,080,000 Direct machine...