Question

c) You are an engineer working for the city of Seoul. You have estimated the annual toll revenues from a newly proposed highw

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Present value of estimated toll:

Annual Toll Receipts 2500000
Years 25
Rate 8%
PV Formula =PV(8%,25,2500000)
PV $26,686,940.47
Add a comment
Know the answer?
Add Answer to:
c) You are an engineer working for the city of Seoul. You have estimated the annual...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are considering purchasing a CNC machine which costs $130,000. This machine will have an estimated service life...

    You are considering purchasing a CNC machine which costs $130,000. This machine will have an estimated service life of 10 years with a net aftier-tax salvage value of $13,000. Its annual after-tax operating and maintenance costs are estimated to be $60,000. To expect an 17 % rate of return on investment, what would be the required minimum annual after-tax revenues? Click the icon to view the interest factors for discrete compounding when /-17 % per year The required minimum annual...

  • The answer is shown in the picture, i want to know how they got it, please show all your work and if you are using excel please show your formulas, Thank You and good luck. Toll lanes on a section of...

    The answer is shown in the picture, i want to know how they got it, please show all your work and if you are using excel please show your formulas, Thank You and good luck. Toll lanes on a section of the 1-40 freeway are being considered in order to reduce traffic congestion and travel times Since this is a government project, the B-C ratio method must be applied in the evaluation. Construction costs of the project are estimated to...

  • You have estimated spot rates as follows: ri = 5.00%, r2 = 5.40%, r3 = 5.70%,...

    You have estimated spot rates as follows: ri = 5.00%, r2 = 5.40%, r3 = 5.70%, r4 = 5.90%, rs = 6.00%. a. What are the discount factors for each date (that is, the present value of $1 paid in year 6)? (Do not round intermediate calculations. Round your answers to 3 decimal places.) Year Discount Factors b. Calculate the PV of the following $1,000 bonds assuming an annual coupon and maturity of: (i) 5%, two-year bond; (ii) 5%, five-year...

  • You are considering purchasing a CNC machine which costs $160,000. This machine will have an estimated service li...

    You are considering purchasing a CNC machine which costs $160,000. This machine will have an estimated service life of 12 years with a net after-tax salvage value of $16,000. Its annual after-tax operating and maintenance costs are estimated to be $56,000. To expect an 16% rate of return on investment, what would be the required minimum annual after-tax revenues? Click the icon to view the interest factors for discrete compounding when i = 16% per year The required minimum annual...

  • Transportation Engineering (25 points) As a junior roadway engineer, you have been asked to contr...

    Transportation Engineering (25 points) As a junior roadway engineer, you have been asked to contribute to the design of a section of roadway that runs through a national park. An endangered deer population has been identified in the area and a wildlife underpass under a vertical curve has been proposed, as shown in the figure below. An existing underpass is perpendicular to the roadway at station 20+91.00 (not necessarily under the center of the curve). The top of the underpass...

  • Thomas Bruggink and David Rose' estimated a regression for the annual team revenue for Major League...

    Thomas Bruggink and David Rose' estimated a regression for the annual team revenue for Major League Baseball franchises (standard errors in parenthesis): Ri= –1522.5 +53.1P: + 1469.4M + 1322.75 — 7376.31 (9.1) (233.6) (1363.6) (2255.7) R2= .682 N = 78 where: R = team revenue from attendance, broadcasting, and concessions (in $000's) P. = the ith team's winning rate (times 1,000) M = the population of the ith team's metropolitan area (in millions) S = a dummy equal to 1...

  • You are considering purchasing a CNC machine which costs $160,000. This machine will have an estimated...

    You are considering purchasing a CNC machine which costs $160,000. This machine will have an estimated service life of 11 years with a net after-tax salvage value of $16,000. Its annual after-tax operating and maintenance costs are estimated to be $51,000. To expect an 19% rate of return on investment, what would be the required minimum annual after-tax revenues? X More Info Th Single Payment Compound Amount Equal Payment Series Present Worth Factor (P/A, i, N) Present Worth Compound Amount...

  • 6–C. Part 1. Internal Service Fund Transactions The Stores and Service Fund of the City of...

    6–C. Part 1. Internal Service Fund Transactions The Stores and Service Fund of the City of Monroe had the following account balances as of January 1, 2017: Debits Credits Cash $28,000 Due from other funds 27,000 Inventory of supplies 27,500 Land 18,000 Buildings 84,000 Accumulated depreciation—buildings $30,000 Equipment 46,000 Accumulated depreciation—equipment 25,000 Accounts payable 19,000 Advance from water utility fund 30,000 Net position 126,500 Totals $230,500 $230,500 Required: a. Open a general journal for the City of Monroe Stores and...

  • QUESTION 3 10 marks You are considering the purchase of a new automated CNC machining centre...

    QUESTION 3 10 marks You are considering the purchase of a new automated CNC machining centre for your company's manufacturing division. The required capital is $3,300,000. The planned life of this machine is estimated at 1 years, after which the salvage value will be $450,000. You have calculated that this machining centre will enable the machining of precision components 24 hours per day (thus increasing gross revenue by $650,000 annually) and more efficiently (by reducing annual labor costs by $180,000)....

  • Toll lanes on a section of the l-40 freeway are being considered in order to reduce traffic congestion and travel times. Since this is a government project, the B-C ratio method must be applied in th...

    Toll lanes on a section of the l-40 freeway are being considered in order to reduce traffic congestion and travel times. Since this is a government project, the B-C ratio method must be applied in the evaluation. Construction costs of the project are estimated to be $18,600,000, and $321,000 per year in operating and maintenance costs are anticipated. In addition, the lanes must be resurfaced every fourth year of their 20-year projected life at a cost of $1,110,000 per occurrence...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT