Question


Chief Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor h
0 0
Add a comment Improve this question Transcribed image text
Answer #1

If you like my explanation, please give a "thumbs up"

Option A $59,790 is the correct answer.

A B D E 1 2 Amount 3 4 5 6 Calculation of total Job cost Calculation Direct Materials Direct labor 615 labour hours * 26 per

Add a comment
Know the answer?
Add Answer to:
Chief Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Chief Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...

    Chief Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $1,550,000, variable manufacturing overhead of $6.00 per labor hour, and 50,000 labor hours. The following data are available for Job 915, which was recently completed: 665 $21,045 Total machine hours Direct materials cost Total direct labor hours Direct labor 615 $26 per...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 70,000 $273,000 $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 50 100 $ 680 $7,000 The...

  • Bolander Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Bolander Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 70,000 $294,000 $ 2.30 Recently, Job M825 was completed with the following characteristics: 20 Number of units in the job Total machine-hours Direct materials Direct labor cost 80 $ 665 $1,840 The total job cost...

  • Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor-hour, and 70,000 direct labor-hours. The company has provided the following data concerning Job T498 which was recently completed: 40 Number of units in the job Total direct labor-hours Direct materials Direct labor cost 80 $...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following datar Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 70,000 $273, eee $ 6.00 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost se 100 $ 680 $7,000...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 96,000 Total fixed manufacturing overhead cost $499,200 Variable manufacturing overhead per direct labor-hour $ 2.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 100 $ 640 $9,600 The...

  • Bolander Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Bolander Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 70,000 $294,000 $ 2.30 Recently, Job M825 was completed with the following characteristics: Number of units in the job Total machine-hours Direct materials Direct labor cost 20 80 $ 665 $1,840 The amount of overhead applied...

  • Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...

    Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours 70,000 Total fixed manufacturing overhead cost $273,000 Variable manufacturing overhead per direct labor-hour $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials Direct labor cost $7,000 The...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 33,000 Total fixed manufacturing overhead cost $ 660,000 Variable manufacturing overhead per machine-hour $ 6.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 715 Direct labor cost $ 1,430 The amount of...

  • Prather Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Prather Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead coat Variable manufacturing overhead per direct labor-hour 50,000 $285,000 $ 3.80 Recently, Job P513 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 10 20 $ 710 $500 The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT