Question

Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price...

Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project:

2021

2022

2023

($ M)

($ M)

($ M)

Costs for the year

90

110

120

Costs incurred to date

90

200

320

Estimated costs to complete

210

120

-

Progress billings during the year

100

120

180

Cash collected during the year

90

130

180

The contract is completed as expected on 30 June 2023. Queens Construction Company uses the percentage-of-completion method to account for its construction contract.

REQUIRED

Provide the numbers for the journal entries below. Assume the stage of completion can be reliably determined. Round the percentage complete (%) to one decimal place (i.e, 0.0%) if necessary.  Complete the six blanks below. (You don't need to provide the numbers for "?")

-------------------------------------

Journal entry to record periodic income recognised:

2021

2022

2023

($M)

($M)

($M)

Dr. Construction in process

Dr. Construction expenses

?

?

?

Cr. Revenue from long-term contract

0 0
Add a comment Improve this question Transcribed image text
Answer #1
For the year ended 2021
Particulars Debit Credit
Construction in progress 90
To cash 90
(being expenditure incurred for construction)
Accounts receivable 100
To billing on construction contract 100
(Being bills raised)
Cash 90
To Accounts receivable 90
(being cash collected during the year)
Construction Expense 90
Construction in progress 30
To construction revenue 120
(being construction revenue recognised)
For the year ending 2022
Construction in progress 110
To cash 110
(being expenditure incurred for construction)
Accounts receivable 120
To billing on construction contract 120
(Being bills raised)
Cash 130
To Accounts receivable 130
(being cash collected during the year)
Construction Expense 110
Construction in progress 36.7
To construction revenue 146.67
(being construction revenue recognised)
For the year ending 2023
Construction in progress 120
To cash 120
(being expenditure incurred for construction)
Accounts receivable 180
To billing on construction contract 180
(Being bills raised)
Cash 180
To Accounts receivable 180
(being cash collected during the year)
Construction Expense 120
Construction in progress 13.3
To construction revenue 133.3
(being construction revenue recognised)
billing on construction contract 400
To construction in progress 400
(being entries on project completion)
% completion calculation
2021 2022 2023
Cost incurred till date 90 200 320
Estimated total cost 300 300 300
% completion 30.0% 66.7% 100%
% completion =cost incurred till date/estimated total cost
Revenue recognised
Cost incurred till date 90 200 320
Estimated total cost 300 300 300
Contract Price 400 400 400
Revenue previously recognised 0 120 146.7
120 146.6667
Revenue recognised =(cost incurred till date/estimated total cost)*Contract price-Revenue previously recognised
Add a comment
Know the answer?
Add Answer to:
Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT