Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project:
2021 |
2022 |
2023 |
|
($ M) |
($ M) |
($ M) |
|
Costs for the year |
90 |
110 |
120 |
Costs incurred to date |
90 |
200 |
320 |
Estimated costs to complete |
210 |
120 |
- |
Progress billings during the year |
100 |
120 |
180 |
Cash collected during the year |
90 |
130 |
180 |
The contract is completed as expected on 30 June 2023. Queens Construction Company uses the percentage-of-completion method to account for its construction contract.
REQUIRED
Provide the numbers for the journal entries below. Assume the stage of completion can be reliably determined. Round the percentage complete (%) to one decimal place (i.e, 0.0%) if necessary. Complete the six blanks below. (You don't need to provide the numbers for "?")
-------------------------------------
Journal entry to record periodic income recognised:
2021 |
2022 |
2023 |
|
($M) |
($M) |
($M) |
|
Dr. Construction in process |
|||
Dr. Construction expenses |
? |
? |
? |
Cr. Revenue from long-term contract |
For the year ended 2021 | ||
Particulars | Debit | Credit |
Construction in progress | 90 | |
To cash | 90 | |
(being expenditure incurred for construction) | ||
Accounts receivable | 100 | |
To billing on construction contract | 100 | |
(Being bills raised) | ||
Cash | 90 | |
To Accounts receivable | 90 | |
(being cash collected during the year) | ||
Construction Expense | 90 | |
Construction in progress | 30 | |
To construction revenue | 120 | |
(being construction revenue recognised) | ||
For the year ending 2022 | ||
Construction in progress | 110 | |
To cash | 110 | |
(being expenditure incurred for construction) | ||
Accounts receivable | 120 | |
To billing on construction contract | 120 | |
(Being bills raised) | ||
Cash | 130 | |
To Accounts receivable | 130 | |
(being cash collected during the year) | ||
Construction Expense | 110 | |
Construction in progress | 36.7 | |
To construction revenue | 146.67 | |
(being construction revenue recognised) | ||
For the year ending 2023 | ||
Construction in progress | 120 | |
To cash | 120 | |
(being expenditure incurred for construction) | ||
Accounts receivable | 180 | |
To billing on construction contract | 180 | |
(Being bills raised) | ||
Cash | 180 | |
To Accounts receivable | 180 | |
(being cash collected during the year) | ||
Construction Expense | 120 | |
Construction in progress | 13.3 | |
To construction revenue | 133.3 | |
(being construction revenue recognised) | ||
billing on construction contract | 400 | |
To construction in progress | 400 | |
(being entries on project completion) |
% completion calculation | |||
2021 | 2022 | 2023 | |
Cost incurred till date | 90 | 200 | 320 |
Estimated total cost | 300 | 300 | 300 |
% completion | 30.0% | 66.7% | 100% |
% completion | =cost incurred till date/estimated total cost |
Revenue recognised | |||
Cost incurred till date | 90 | 200 | 320 |
Estimated total cost | 300 | 300 | 300 |
Contract Price | 400 | 400 | 400 |
Revenue previously recognised | 0 | 120 | 146.7 |
120 | 146.6667 | ||
Revenue recognised | =(cost incurred till date/estimated total cost)*Contract price-Revenue previously recognised |
Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...