Actual Output | 24,800 | |||||
Multiply: Std Variable OH cost per unit | 27.00 | |||||
Variable OH as per Flexible Budget | 6,69,600 | |||||
Actual Variable OH incurred | 6,12,300 | |||||
Variable OH Spending variance | 57,300 | Fav | ||||
(Favorable as actual overheads incurred is lower) | ||||||
Variable Mfg OH spending variance | 57,300 | Fav |
Troubleshooting 24 Help Check Part 5 of 6 Required information The following information applies to the...
5 Help Chee of 6 Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 20:41 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit $ 45.00 42.00 27.00 $ 114.00 The company...
Help Save 6 Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 0:47 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.00 42.00 27.00 Total standard cost per unit $ 114.00 The company planned to...
21 Coby Prochinhas Valve art 2 of 6 Required information The following information applies to the questions displayed below) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 02:22:06 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit $ 45.00 42.00 27.00 Print...
shooting Sa 3 Help Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: of 6 21:25 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit $ 45.ee 42.00 27.00 $ 114.00 The...
Ultration of 6 (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 53:01 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.00 42.00 27.00 t Total standard cost per unit $ 114.00 The company planned to produce...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Saved Coper Products Inc. has a 22 Help Save LE 3 of 6 Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 2:21:44 Direct materials: 5 kg at $9.80 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Required information [The following information applies to the questions displayed below) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $5 per hour Total standard cost per unit $ 48.ee 42.00 15.00 $ 105.00 The company planned to produce and sell 19,000...
Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: $ 45 42 Direct materials: 5 pounds at $9 per pound Direct labor: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit 27 $ 114 The planning budget for March was based...