Question

21 Coby Prochinhas Valve art 2 of 6 Required information The following information applies to the questions displayed below)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Computation of direct material quantity variance for month of March :

1. Standard quantity required per unit

5 kgs

2. Standard quantity required in for actual production

(24,800 units )

SQ

1,24,000 kgs

(24,800 units* 5 kgs)

3. Actual quantity required for actual production

( 24,800 units)

AQ

1,55,000 kgs

4. Actual price per kg

AP

$ 7.20

5. Standard price per kg

SP

$ 9.00

Direct Material Quantity variance

SQ* SP- AQ* SP

1,24,000 kgs*$ 9.00 -1,55,000 kgs *$ 9.00

$ 11,16,000 - $ 13,95,000

$ 2,79,000 U (Unfavorable)

Conclusion:

Material Quantity variance

$ 2,79,000 U (Unfavorable)

Thankyou !!!!!

Add a comment
Know the answer?
Add Answer to:
21 Coby Prochinhas Valve art 2 of 6 Required information The following information applies to the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ultration of 6 (The following information applies to the questions displayed below.) Preble Company manufactures one...

    Ultration of 6 (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 53:01 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.00 42.00 27.00 t Total standard cost per unit $ 114.00 The company planned to produce...

  • Help Save 6 Required information [The following information applies to the questions displayed below.) Preble Company...

    Help Save 6 Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 0:47 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.00 42.00 27.00 Total standard cost per unit $ 114.00 The company planned to...

  • 5 Help Chee of 6 Required information (The following information applies to the questions displayed below.)...

    5 Help Chee of 6 Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 20:41 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit $ 45.00 42.00 27.00 $ 114.00 The company...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $9.00 per kg $ 45.00     Direct labour: 3 hours at $14 per hour 42.00     Variable overhead: 3 hours at $9 per hour 27.00     Total standard cost per unit $ 114.00   The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Troubleshooting 24 Help Check Part 5 of 6 Required information The following information applies to the...

    Troubleshooting 24 Help Check Part 5 of 6 Required information The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 02-2007 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.ee 42.ee 27.00 Print Total standard cost per unit...

  • Saved Coper Products Inc. has a 22 Help Save LE 3 of 6 Required information [The...

    Saved Coper Products Inc. has a 22 Help Save LE 3 of 6 Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 2:21:44 Direct materials: 5 kg at $9.80 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit...

  • shooting Sa 3 Help Required information (The following information applies to the questions displayed below.) Preble...

    shooting Sa 3 Help Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: of 6 21:25 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit $ 45.ee 42.00 27.00 $ 114.00 The...

  • Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product....

    Required information (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $9.00 per kg Direct labour: 3 hours at $15 per hour Variable overhead: 3 hours at 55 per hour $ 54.00 45.00 15.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20.000...

  • Required information [The following information applies to the questions displayed below) Preble Company manufactures one product....

    Required information [The following information applies to the questions displayed below) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $5 per hour Total standard cost per unit $ 48.ee 42.00 15.00 $ 105.00 The company planned to produce and sell 19,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT