Question

Spin Cyde Aitecture uses the activity Boopy headaches at the heat the down $250,000and construction oversight $122.850. The c
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Based on the information available in the question, we can answer as follows:-

Requirement A:-

The predetermined overhead activity rate for each activity is calculated as :-

=Total cost of the activity/Estimated use of cost drivers

Initial Concept Formation = $49,400/20

Inital Concept Formation = $2,470 per project change

(Note:- The cost of the Initial concept formation activity is not clearly visible. However, based on our observation it most probably resembles $49,400. Hence we have used the $49,400 in our calculation above. If it is $49,000, then the cost per project change will be = $2,450 per change)

Design = $260,000/130,000

Design = $2 per Square foot

Construction oversight = $122,850/ 105

Construction oversight = $1,170 per month

Requirement B:-

Initial Concept Formation - Product Level as the inital concept varies from product to product.

Design - Unit level as it varies from unit to unit.

Construction oversight - Batch level as the costs relate to the batch of units produced over the course of time(months).

Please let me know if you have any questions via comments and all the best :) !

Add a comment
Know the answer?
Add Answer to:
Spin Cyde Aitecture uses the activity Boopy headaches at the heat the down $250,000and construction oversight...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has...

    Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $45,400; design $290,000; and construction oversight $122,850. The cost drivers and estimated use are as follows. Estimated Use of Cost Drivers per Activity Activities Initial concept formation Design Construction oversight Cost Drivers Number of project changes Square feet Number of...

  • Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has...

    Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $41,000; design $334,000; and construction oversight $116,550. The cost drivers and estimated use are as follows. Activities Cost Drivers Estimated Use of Cost Drivers per Activity Initial concept formation Number of project changes 25 Design Square feet 167,000 Construction oversight...

  • NEXT Brief Exercise 17-12 Spin Cycle Architecture uses three activity pools to apply overhead to its...

    NEXT Brief Exercise 17-12 Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $47,800; design $447,000; and construction oversight $116,550. The cost drivers and estimated use are as follows. Activities Initial concept formation Design Construction oversight Cost Drivers Number of project changes Square feet Number of months Estimated Use...

  • 299-830c-13050501042c/question/4 lass Question 5 of 6 - / 1 Spin Cycle Architecture uses three activity pools...

    299-830c-13050501042c/question/4 lass Question 5 of 6 - / 1 Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $40,000; design $300,000; and construction oversight $100,000. The cost drivers and estimated use are as follows. Estimated Use of Cost Activities Cost Drivers Drivers per Activity Initial concept formation Number of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT