Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $41,000; design $334,000; and construction oversight $116,550. The cost drivers and estimated use are as follows.

Activities

Cost Drivers

Estimated Use of Cost
Drivers per Activity

Initial concept formation Number of project changes 25
Design Square feet 167,000
Construction oversight Number of months 105


(a) Compute the predetermined overhead rate for each activity.

Overhead Rate

Initial concept formation $ per project change
Design $ per square foot
Construction oversight $ Per month


(b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.

Activities

Level

Initial concept formation

Product-levelUnit-levelFacility-levelBatch-level

Design

Batch-levelProduct-levelFacility-levelUnit-level

Construction oversight

Batch-levelFacility-levelUnit-levelProduct-level

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution-

a)

Overhead Rate
Initial concept formation $1640 Per project change
Design $2 per square foot
Construction oversight $1110 per month

Working- Predetermined overhead rate = Estimated overhead / Estimated allocation base

*Initial concept formation = ($41000/25) = $1640

* Design = ($334000 / 167000) = $2

* Construction oversight = ($116550/105) = $1110

b)

Activities Level
Initial concept formation Product level
Design Unit level
Construction oversight Batch level
Add a comment
Know the answer?
Add Answer to:
Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has...

    Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $45,400; design $290,000; and construction oversight $122,850. The cost drivers and estimated use are as follows. Estimated Use of Cost Drivers per Activity Activities Initial concept formation Design Construction oversight Cost Drivers Number of project changes Square feet Number of...

  • NEXT Brief Exercise 17-12 Spin Cycle Architecture uses three activity pools to apply overhead to its...

    NEXT Brief Exercise 17-12 Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $47,800; design $447,000; and construction oversight $116,550. The cost drivers and estimated use are as follows. Activities Initial concept formation Design Construction oversight Cost Drivers Number of project changes Square feet Number of months Estimated Use...

  • 299-830c-13050501042c/question/4 lass Question 5 of 6 - / 1 Spin Cycle Architecture uses three activity pools...

    299-830c-13050501042c/question/4 lass Question 5 of 6 - / 1 Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $40,000; design $300,000; and construction oversight $100,000. The cost drivers and estimated use are as follows. Estimated Use of Cost Activities Cost Drivers Drivers per Activity Initial concept formation Number of...

  • Spin Cyde Aitecture uses the activity Boopy headaches at the heat the down $250,000and construction oversight...

    Spin Cyde Aitecture uses the activity Boopy headaches at the heat the down $250,000and construction oversight $122.850. The cost versandduse areas mated the Cost Cast Drivers Drivers per Activity Initial concept formation Number of project changes 20 Design Suare feet 110.000 Construction oversight Number of month 105 (a) Compute the predetermined overhead rate for each city Initial concept formation $ per pretthange Coconvert () Cassy each of these activities as bevel the date of Activities Intial concept formation Design Construction...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $280,460 Number of machine hours 67,500 Number of design hours 70,070 Number of batches Estimated Cost Driver 75,800 7,500 490 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in...

  • ! Required information Gable Company uses three activity cost pools. Each pool has a cost driver....

    ! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT