Materials | Conversion costs | |
T12 Tables | 20600 | 19364 |
C10 Chairs | 16480 | 16377 |
Explanations :-
Materials | ||
T12 Tables | C10 Chairs | |
(20600 * 100%) = 20600 | (16480 * 100%) = 16480 | |
Conversion costs | ||
T12 Tables | C10 Chairs | |
Units started & completed | 17510 | 15965 |
Ending WIP | 1854 | 412 |
19364 | 16377 |
Materials | Conversion costs | Total costs | |
Unit costs-T12 Tables | $ 19.00 | $ 18.00 | $ 37.00 |
Unit costs-C10 Chairs | $ 18.00 | $ 13.51 | $ 31.51 |
Explanations:-
Materials | ||
T12 Tables | C10 Chairs | |
Cost incurred | $391,400 | $296,640 |
÷ Equivalent units | 20600 | 16480 |
$ 19.00 | $ 18.00 | |
Conversion costs | ||
T12 Tables | C10 Chairs | |
Cost incurred | $348,552 | $221,244 |
÷ Equivalent units | 19364 | 16377 |
$ 18.00 | $ 13.51 |
T12 Tables | ||
Cost accounted for: | ||
Transferred out | $647,870 | |
Work in process | ||
Materials | $58,710 | |
Conversion costs | $33,372 | $92,082 |
Total costs | $ 739,952 | |
C10 Chairs | ||
Cost accounted for: | ||
Transferred out | $503,048 | |
Work in process | ||
Materials | $9,270 | |
Conversion costs | $5,566 | $14,836 |
Total costs | $ 517,884 |
Equivalent units | ||||
Quantities | Physical units | Materials | Conversion costs | |
Units to be accounted for | ||||
Work in process July 1 | ||||
Started into production | 20600 | |||
Total units | 20600 | |||
Units accounted for | ||||
Transferred out | 17510 | 17510 | 17510 | |
Work in process July 31 | 3090 | 3090 | 1854 | |
Total units | 20600 | 20600 | 19364 | |
Costs | Materials | Conversion costs | Totals | |
Unit costs | ||||
Total costs | $391,400 | $348,552 | $739,952 | |
Equivalent units | 20600 | 19364 | ||
Unit costs | $19 | $18 | $37 | |
Cost to be accounted for | ||||
Work in process July 1 | ||||
Started into production | $739,952 | |||
Total costs | $739,952 | |||
Cost Reconciliation Schedule | ||||
Costs accounted for | ||||
Transferred out | $647,870 | |||
Work in process July 31 | ||||
Materials | $58,710 | |||
Conversion costs | $33,372 | $92,082 | ||
Total costs | $ 739,952 |
FULL SCREEN PRINTER VERSION BACK NEXT Problem 17-3A Thakin Industries Inc, manufactures dorm furniture in separate...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 24,600 19,680 Work in process units, July 31 3,690...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 25,000 20,000 Work in process units, July 31 3,750...
Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first processin products in two different manufacturing plants are as follows. Cutting Department g two T12-Tabes CIO-Chairs Production Date -July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 17,600 22,000 3,300 Cost Date-July Work in...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...
Thakin Industries Inc. manufactures dorm furniture in separate processes Production and cost data for the first process in making two products in tw Cutting Department Plant 1 Plant 2 Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete T12-Tables c10-Chairs 0 17,500 700 80 G. 19,500 3,100 60 Cost Data-July Work in process, July1 s0 390,000 234, 700 112,240 $0 Materials 280,000 113,000 112,680 Labor Overhead...
NEED HELP ASAP CALCULATOR FULL SCREEN PRINTER VERSION BACK NET Problem 3-3A (Video) (Part Level Submission) Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department T12-Tables Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent...
Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incur uniformly, Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,400 3,360 17,920 560 60...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...
Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conver Cutting Department Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July 17,600 Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 550 Cost Data-July Work in process, July 1 Materials Labor Overhead Total 418,000 257,840 114,400 $790,240...
Problem 17-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-Jul Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete...