Question

Meiger Mining, Inc., has just discovered two new mining sites for iron ore. Geologists and engineers...

Meiger Mining, Inc., has just discovered two new mining sites for iron ore. Geologists and engineers have come up with the estimates on the following page regarding costs and ore yields if the mines are opened.

Site A Site B
Variable extraction costs per ton $ 3.80 $ 4.00
Fixed costs over the life of the mine:
Blasting $ 150,000 $ 185,000
Construction 225,000 240,000
Maintenance 25,000 20,000
Restoration costs 40,000 35,000
Total fixed costs $ 440,000 $ 480,000
Total tons of ore that can be extracted over the life of the mine: 200,000 160,000

Meiger’s owners currently demand a return of 20 percent of the market price of iron ore.

Required:

a. If the current market price of iron ore is $8 per ton, what is Meiger’s target cost per ton?

b-1. Given the $8 market price, compute the total cost per ton for Site A and Site B if fixed overhead costs are assigned to products on the basis of estimated tons of ore that can be extracted over the life of the mine.

b-2. Should either of the mines be opened?

c-1. The engineer working on Site B believes that if a custom conveyor system is installed, the variable extraction cost could be reduced to $3 per ton. The purchase price of the system is $25,000, but the costs to restore the site will increase to $45,000 if it is installed. Given the current $8 market price, compute the total cost per ton for site B.

c-2. Should Meiger install the conveyor and open Site B?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a. If the current market price of iron ore is $8 per ton, then Meiger's target cost per ton is,

$8.0 - ($8.0X 20%) = $6.4 per Ton

b-1. Total cost per ton:

For site A :

Variable cost per ton +Fixed cost per ton

$3.80 +($440,000÷ 200,000 tons) = $6 per ton

For Site B:

$4.00 +( $480,000 ÷ 160,000) = $7 per ton

b-2: to meet the demand of 20% only site A shoudl be opened because its cost per ton is less then the targeted cosst of $6.40 and since the cost per ton for site B is $7 it will not give the desired return.

c. Total Cost per ton for site B:

Variable cost per ton +Fixed cost per ton

$3.00 +[$185,000+240,000+20,000+25,000+45,000)÷ 160,000tons] = $6.22 per ton

Current Market Price: $8.00 , so target cost per ton is,

$8.00 - ($8.00X 20%) = $6.4 per Ton

Yes, Meiger should install the conveyor and open Site B,because the cost per ton after installing of conveyer is less then the targeted cost of $6.40.

Add a comment
Know the answer?
Add Answer to:
Meiger Mining, Inc., has just discovered two new mining sites for iron ore. Geologists and engineers...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2018, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of...

    In 2018, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of $564,000 were incurred to develop the mine. Geologists estimated that 600,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $104,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $252,000. These structures have a useful life of 10 years. The structures cannot...

  • ABC Mining Company has been operating an iron ore mine for the last 10 years. With...

    ABC Mining Company has been operating an iron ore mine for the last 10 years. With the passage of time, the company finds that the iron ore extracted is declining each year. The company just paid a dividend of $2 per share and announced that the amount would decline at a rate of 3% each year for the foreseeable future. The required return for ABC Mining shares is 13% (a) What is the price per share of ABC Mining Company?...

  • In 2018, the Marion Company purchased land containing a mineral mine for $1,660,000. Additional costs of...

    In 2018, the Marion Company purchased land containing a mineral mine for $1,660,000. Additional costs of $723,000 were incurred to develop the mine. Geologists estimated that 700,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $108,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $455,000. These structures have a useful life of 10 years. The structures cannot...

  • Problem 11-7 Depletion; change in estimate (L011-3. 11-5) In 2018, the Marion Company purchased and containing...

    Problem 11-7 Depletion; change in estimate (L011-3. 11-5) In 2018, the Marion Company purchased and containing a mineral mine for $1,300,000. Additional costs of $493.000 were incurred to develop the mine Geologists estimated that 340.000 tons of ore would be extracted. After the one is removed, the land will have a Tesale value of $110.000 To aid in the extraction Marion built various structures and small storage buildings on the site at a cost of $117300. These structures have a...

  • In 2021, the Marion Company purchased land containing a mineral mine for $1,740,000. Additional costs of...

    In 2021, the Marion Company purchased land containing a mineral mine for $1,740,000. Additional costs of $676,000 were incurred to develop the mine. Geologists estimated that 400,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $116,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $184,000. These structures have a useful life of 10 years. The structures cannot...

  • Please show ALL EXCEL FORMULAS! BETHESDA MINING COMPANY Bethesda Mining is a midsized coal mining company...

    Please show ALL EXCEL FORMULAS! BETHESDA MINING COMPANY Bethesda Mining is a midsized coal mining company with 20 mines located in Ohio, Pennsylvania, West Virginia, and Kentucky. The company operates deep mines as well as strip mines. Most of the coal mined is sold under contract, with excess production sold on the spot market. The coal mining industry, especially high-sulfur coal operations such as Bethesda, has been hard-hit by environmental regulations. Recently, however, a combination of increased demand for coal...

  • In 2021, the Marion Company purchased land containing a mineral mine for $1,450,000. Additional costs of...

    In 2021, the Marion Company purchased land containing a mineral mine for $1,450,000. Additional costs of $547,000 were incurred to develop the mine. Geologists estimated that 370,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $110,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $133,200. These structures have a useful life of 10 years. The structures cannot...

  • BETHESDA MINING COMPANY Bethesda Mining is a midsized coal raining company with 20 mines located in...

    BETHESDA MINING COMPANY Bethesda Mining is a midsized coal raining company with 20 mines located in Ohio, Pennsyl- vania, West Virginia, and Kentucky. The company operates deep mines as well as strip mines. Most of the coal mined is sold under contract, with excess production sold on the spot market. The coal mining industry, especially high-sulfur coal operations such as Bethesda, has been hard-hit by environmental regulations. Recently, however, a combination of increased demand for coal and new pollution reduction...

  • In 2021, the Marion Company purchased land containing a mineral mine for $2,050,000. Additional costs of...

    In 2021, the Marion Company purchased land containing a mineral mine for $2,050,000. Additional costs of $843,000 were incurred to develop the mine. Geologists estimated that 490,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $100,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $205,800. These structures have a useful life of 10 years. The structures cannot...

  • Bethesda Mining is a mid-sized coal mining company with 20 mines located in Ohio, Pennsylvania, West...

    Bethesda Mining is a mid-sized coal mining company with 20 mines located in Ohio, Pennsylvania, West Virginia, and Kentucky. The company operates deep mines as well as strip minds. Most of the coal mined is sold under contract, with excess production sold on the spot market.The coal mining industry, especially high-sulfur coal operations such as Bethesda, has been hard-hit by environmental regulations. Recently, however, a combination of increased demand for coal and new pollution reduction technologies has led to an...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT