Milberg Co. uses absorption costing and standard costing to improve cost control.
In 2020, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500.
The following data on actual results are provided for the month of November 2020.
Materials purchased |
20,000 |
units |
Direct labour costs incurred |
$36,000 |
|
Total of direct labour rate and efficiency variances |
500 |
F |
Actual wage rate ($0.20 less than standard) |
4.80 |
|
Underapplied variable overhead costs |
1,065 |
U |
Total underapplied fixed and variable overhead costs |
2,256 |
U |
Materials price variance |
200 |
F |
Materials efficiency variance |
610 |
F |
Price of purchased materials |
0.60 |
per unit |
Materials used |
15,000 |
units |
Instructions
Identify and calculate as many different variances as you can for 2020.
Please explain it well
Answer
1) | Material Price Variance | ||||||
[Standard Price- Actual Price] X Actual Quantity = 200 F | |||||||
[Standard Price- 0.6] X 20,000 units = 200 F | |||||||
Standard Price= 0.61 per unit | |||||||
2) | Material Effeciency Variance | ||||||
[ Standard units - Actual Units] X Standard Price = 610 F | |||||||
[Standard units- 15,000 units] X 0.61 per unit = 610 F | |||||||
Standrad Units= 16,000 units | |||||||
3) | Material Cost Variance | ||||||
= Material Price Variance + Material Effeciency Variance | |||||||
= 200 F + 610 F | |||||||
= 810 F | |||||||
4) | Labour Cost Variance | ||||||
Labour Rate Variance + Labour Effeciency Variance = 500 F | |||||||
Standard Labour Rate = Atual Wage Rate + $0.2 | |||||||
= $4.8 + $0.2 | |||||||
=$5 | |||||||
Actual Labour Hour = $36,000/4.8 = $7,500 | |||||||
Budgeted monthly Direct Labour Hours = 10,000 | |||||||
Therefore, Standard Total Labour Cost are computed as under | |||||||
Labour Cost Variance = 500 F | |||||||
[Standard Total Labour Cost - Actaul Total Labour Cost] = 500 F | |||||||
[Standard Total Labour Cost - $36,000)= 500 F | |||||||
Standard Total Labour Cost = $36,500 | |||||||
Standard Hour = $36,500/5 = 7,300 | |||||||
5) | Labour Price Variance | ||||||
[Standard Rate - Actual Rate] X Actual Hours | |||||||
[$5 - $4.8] X 7500 | |||||||
= $1,500 F | |||||||
6) | Labour Effeciency Variance | ||||||
[Standard Hour - Actaul Hour] X Standard Rate | |||||||
=[ 7300 - 7500] X 5 | |||||||
= $1,000 U |
Milberg Co. uses absorption costing and standard costing to improve cost control. In 2020, the total...
Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. Solve for: Variable Overhead Spending Variance Variable Overhead Efficiency Variance Variable Overhead Total...
Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. calculate the following variances: Material Price Variance Materials Quantity Variance Total Materials Variance...
Question 5 (23 marks) Cleanup Ltd produces an industrial chemical and uses a standard costing system to keep tight control over its costs. At the beginning of 2017, the following standard cost sheet (for one unit) was prepared: Direct materials (10kg @ $1.60/kg) Direct labour (0.75 hrs @$18.00hr) Fixed overhead (? /hr) Variable overhead (? /hr) Standard cost per unit $16.00 13.50 3.00 2.25 $34.75 Manufacturing overhead is allocated based on direct labour hours. The budgeted overhead rate is determined...
sol th Question 4 (10 marks) The following is the standard cost card for X Company's only product: Direct materials, 4 metres at $4.00 Direct labour, 1.5 hours at $10.00 Variable overhead, 1.5 hours at $3.00 Fixed overhead, 1.5 hours at $7.00 Standard cost per unit $16.00 $15.00 $4.50 $10.50 $46.00 The company manufactured and sold 18 000 units of product during the year. A total of 70,200 metres of material was purchased durine the vear at cost of $4.20...
Ander's Clothing manufactures embroidered jackets. The company uses a standard cost system to control manufacturing costs. The following data represent the standard unit cost of a jacket: i Data Table $4.15 per sq. ft.) Direct materials 3.0 sq. ft x 12.45 Direct labor $9.70 per hour) ( 2,0 hours x 19.40 Manufacturing overhead: Variable 2.0 hours x $0.68 per hour) 1.36 4.40 5.76 2.0 hours x $2.20 per hour) Fixed 37.61 Total standard cost per jacket Fixed overhead in total...
1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...
ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...
You have been given the following list of variances for the Pennadi Company: Direct materials price variance $ 16,800 U Direct materials quantity variance 12,000 U Direct labour rate variance 16,270 F Direct labour efficiency variance 27,000 U Variable overhead spending variance 3,120 U Variable overhead efficiency variance 6,000 U Fixed overhead budget variance 5,000 U Fixed overhead volume variance 53,250 F You have also been given the following information: Actual units produced 25,000 Budgeted units...
Muddy Duck Manufacturing (MDM) Inc.’s costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead, both fixed and variable, is allocated to products on the basis of standard direct manufacturing labour hours (DMLH). At the beginning of 2017, MDM adopted the following standards for its manufacturing costs: Input Cost per output unit Direct materials 3kg @ $5 per kg $15 Direct manufacturing labour 5 hours @ $15 per hour 75 Manufacturing overhead: Variable $6 per...
ABC Company uses a standard costing system for production costing and control Standard direct labor hours based on practical capacity are used to compute overhead rates. The standard cost for the one of its products is as follows: Quantity Cost per unit Total Cost 4.0 kilograms $ 10.00 $ 40.00 2.6 hours 31.20 2.6 hours 10.00 26.00 2.6 hours 6.00 15.60 + Raw material Direct labor Variable overhead Fixed overhead 12.00 Annual practical capacity 60,000 units NU UN During the...