Question

Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates
Using the ABC data, determine the total amount of overhead cost assigned to each product. Complete this question by entering
Using the ABC data, determine the total amount of overhead cost assigned to each product. Complete this question by entering
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1) Calculation of Activity Rates
Activity Cost pool Expected OH Expected Activity Activity Rate
Labour related            269,100                        29,900                 9.00 per DLH
Purchase Orders              11,000                              220              50.00 per ORDER
Parts Management              78,440                              106            740.00 per part type
Board Etching              85,050                          1,890              45.00 per board
General Factory            242,400                        20,200              12.00 per MH
2) Overehad cost assigned to each product
Activity Cost pool Activity Rate Product A Activity Cost assigned to product A Product B Activity Cost assigned to product B Product C Activity Cost assigned to product C Product D Activity Cost assigned to product D
Labour related                   9.00                          7,500            67,500          13,400          120,600          3,800            34,200          5,200            46,800
Purchase Orders                50.00                                66              3,300                  30              1,500                32              1,600                92              4,600
Parts Management              740.00                                29            21,460                  19            14,060                47            34,780                11              8,140
Board Etching                45.00                              580            26,100                750            33,750              560            25,200                 -                       -  
General Factory                12.00                          2,600            31,200            7,300            87,600          3,700            44,400          6,600            79,200
Total Cost assigned          149,560          257,510          140,180          138,740
Add a comment
Know the answer?
Add Answer to:
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 284.000 $ 6,790 $ 71,340 $ 57,900 $ 229,900 Expected Activity 35,500 DLHS 194 orders 82 part types 1.930 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 156,000 $ 11,000 $ 80,000 $ 90,000 $ 180,000 Expected Activity 26,000 DLHS 220 orders 100 part types 2,000 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHs 221 orders 99 part types 1,820 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 231,600 $ 15,015 $ 95,200 $ 106,800 $ 184,500 Expected Activity 38,600 DLHS 231 orders 112 part types 1,780 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHS 221 orders 99 part types 1,820 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools Activity Measure Expected Overhead Expected Activity Activity Cost Pool Labor-related Purchase orders Parts management Cost Direct labor-hours Number of orders Number of part types S 284,000 35,500 DLHs $ 6,790 S 194 orders 71,340 82 part types Number of boards Machine-hours S 57,900 $ 229,900 20,900 MH:s 1,930 boards Board etching...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Expected Measure Overhead Expected Activity Cost Pool Cost Activity Labor-related Direct labor-hours $380,000 38.000 DLHS Purchase orders Number of orders $11.935 217 orders Parts Number of part $ 79,500 1 06 part types management types Board etching Number of boards $93.000 1,860 boards General factory Machine-hours $240,500 18.500 MHS Required:...

  • Sultan Company uses an activity-based costing system At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Expected Measure Overhead Expected Activity Cost Pool Cost Activity Labor-related Direct labor-hours $ 148,000 29,600 DLHs Purchase orders Number of orders $ 15,180 253 orders Parts management Number of part types $ 85,680 102 part types Board etching General factory Number of boards Machine-hours $ 99,550 $ 162,400 1,810 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 269,100 $ 11,000 $ 78,440 $ 85,050 $ 242,400 Expected Activity 29,900 DLHS 22e orders 106 part types 1.890...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 148,000 $ 15,180 $ 85,680 $ 99,550 $ 162,400 Expected Activity 29,600 DLR 253 orders 102 part types 1,810 boards...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT