Question

eBook Calculator Print Item Silven Company has identified the following overhead activities, costs, and activity drivers for
0 0
Add a comment Improve this question Transcribed image text
Answer #1
A B C= A/B
Particulars Expected Cost Activity Capacity Activity Allocation Rate
Setting up Equipment 135,000 120 1,125 per Setup
Ordering Materials 10,200 600 17 per Order
Machining 89,600 11,200 8 per Machine Hour
Receiving 17,280 1,080 16 per Receiving Hour

Model X

A. B. C=A*B

Particulars Activity Allocation Rate Activity Capacity for Model X Total Overhead
Setting up Equipment 1,125 80 90,000
Ordering Materials 17 200 3,400
Machining 8 6,400 51,200
Receiving 16 360 5,760
Total Overhead 150,360

Model Y

A. B. C= A*B

Particulars Activity Allocation Rate Activity Capacity for Model X Total Overhead
Setting up Equipment 1,125 40 45,000
Ordering Materials 17 400 6,800
Machining 8 4,800 38,400
Receiving 16 720 11,520
Total Overhead 101,720

Requirement 2

Ordering Materials = $ 10,200

Ratio of Setting up Equipment to Machining = 135,000:89,600

Ordering Materials Cost allocated to Setting up Equipment = 10,200 * 135,000 / 224,600

Ordering Materials Cost allocated to Setting up Equipment = $ 6,131

Ordering Materials Cost allocated to Machining = 10,200 * 89,600 / 224,600

Ordering Materials Cost allocated to Machining = $ 4,069

Receiving Costs = $ 17,280

Ratio of Setting up Equipment to Machining = 135,000 : 89,600

Receiving Costs allocated to Setting up Equipment = 17,280 * 135,000 / 224,600

Receiving Costs allocated to Setting up Equipment = $ 10,386

Receiving Costs allocated to Machining = 17,280 * 89,600 / 224,600

Receiving Costs allocated to Machining = $ 6,894

Main Work

Total Setting up Costs after allocation = 135,000 + 6,131 + 10,386 = $ 151,517

Total Machining Costs after Allocation = 89,600 + 4,069 + 6,894 = $ 100,563

A. B. C= A/B

Particulars Expected Cost Activity Capacity Activity Allocation Rate
Setting up Equipment 151,517 120 1,262.64 per Setup
Machining 100,563 11,200 8.98 per Machine Hour

For Model X

For Total Amount = Activity Allocation Rate * Activity Capacity

Particulars Activity Allocation Rate Activity Capacity Total Amount
Setting up Equipment 1,262.64 80 101,011
Machining 8.98 6400 57,465
Total Overhead 158,476

For Model Y

Particulars Activity Allocation Rate Activity Capacity Total Amount
Setting up Equipment 1,262.64 40 50,506
Machining 8.98 4,800 43,098
Total Overhead

93,604

Question 3

Overhead Cost of Model X as per ABC = $ 150,360

Overhead Cost of Model X as per Question 2 = $

Cost = 158,476

Change in Overhead Cost = 158,476 - 150,360 = $ 8,116

Percentage Error = Change / Overhead Cost as per ABC * 100

Percentage Error = 8,116 / 150,360 * 100 = 5.40%

For Model Y

Overhead Cost of Model Y as per ABC = $ 101,720

Overhead Cost of Model Y as per Question 2 = $

Cost = 93,604

Change in Overhead Cost = 93,604 - 101,720= $ 8,116

Percentage Error = Change / Overhead Cost as per ABC * 100

Percentage Error = (8,116) / 101,720 * 100 = (7.98%)

Add a comment
Know the answer?
Add Answer to:
eBook Calculator Print Item Silven Company has identified the following overhead activities, costs, and activity drivers...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $141,000 Number of setups 120 Ordering materials 24,000 Number of orders 1,200 Machining 105,000 Machine hours 8,750 Receiving 26,280 Receiving hours 1,095 Silven produces two models of cell phones with the following expected activity demands: Model Y Model X X 4,200 8,400 Units completed Number of setups 80 40 400 800 Number of orders...

  • Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $129,000 Number of setups 120 Ordering materials 15,300 Number of orders 900 Machining 92,400 Machine hours 11,550 Receiving 16,800 Receiving hours 1,050 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y 5,900 11,800 80 40 300 Units completed Number of setups Number of orders Machine hours...

  • Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for...

    Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost           Activity Driver Activity Capacity Setting up equipment $135,000           Number of setups 120 Ordering materials 10,800           Number of orders 600 Machining 119,000           Machine hours 11,900 Receiving 19,200           Receiving hours 960 Silven produces two models of cell phones with the following expected activity demands:       Model X       Model Y Units completed 4,300   8,600 Number...

  • Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for...

    Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $129,000 Number of setups 120 Ordering materials 15,300 Number of orders 900 Machining 92,400 Machine hours 11,550 Receiving 16,800 Receiving hours 1,050 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 5,900 11,800 Number of setups 80 40 Number of orders...

  • custom products. VE 2 Exercise 4.22 Approximately Relevant ABC Silven Company has identified the following overhead...

    custom products. VE 2 Exercise 4.22 Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment S126,000 Number of setups 150 Ordering materials 18,000 Number of orders 900 Machining 126,000 Machine hours Receiving 30,000 Receiving hours 1,250 10.500 Silven produces two models of cell phones with the following expected activity demands: Model X 5,000 Model Y 10,000 100 Units completed Number...

  • Activity Expected Cost           Activity Driver Activity Capacity Setting up equipment $132,000           Number of setups...

    Activity Expected Cost           Activity Driver Activity Capacity Setting up equipment $132,000           Number of setups 120 Ordering materials 27,600           Number of orders 1,200 Machining 118,300           Machine hours 9,100 Receiving 34,320           Receiving hours 1,320 Silven produces two models of cell phones with the following expected activity demands:       Model X       Model Y Units completed 5,900   11,800 Number of setups 80   40 Number of orders 400   800 Machine hours 5,200   3,900 Receiving hours 440   880 1. Determine...

  • Approximately Relevant ABCSilven Company has identified the following overhead activities, costs, and activity drivers for the...

    Approximately Relevant ABCSilven Company has identified the following overhead activities, costs, and activity drivers for the coming year:Silven produces two models of cell phones with the following expected activity demands:Required:1. Determine the total overhead assigned to each product using the four activity drivers.2. Determine the total overhead assigned to each model using the two most expensive activities. The costs of the two relatively inexpensive activities are allocated to the two expensive activities in proportion to their costs.3. Using ABC as...

  • Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $469,800 Number of setups 580 Ordering costs 348,000 Number of orders 17,400 Machine costs 747,000 Machine hours 41,500 Receiving 462,000 Receiving hours 10,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $779,000 Direct labor $471,000 $484,000 Units completed 15,600 7,200...

  • Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...

    Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $480,850 Number of setups 590 Ordering costs 425,500 Number of orders 18,500 Machine costs 700,400 Machine hours 41,200 Receiving 298,800 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $570,000 $821,000 Direct labor $462,000 $472,000 Units completed 16,500 8,800...

  • Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs,...

    Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $492,660 Number of setups 630 Ordering costs 361,200 Number of orders 17,200 Machine costs 882,000 Machine hours 42,000 Receiving 399,000 Receiving hours 9,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $599,000 $ 780,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT