A | B | C= A/B | ||
Particulars | Expected Cost | Activity Capacity | Activity Allocation Rate | |
Setting up Equipment | 135,000 | 120 | 1,125 | per Setup |
Ordering Materials | 10,200 | 600 | 17 | per Order |
Machining | 89,600 | 11,200 | 8 | per Machine Hour |
Receiving | 17,280 | 1,080 | 16 | per Receiving Hour |
Model X
A. B. C=A*B
Particulars | Activity Allocation Rate | Activity Capacity for Model X | Total Overhead |
Setting up Equipment | 1,125 | 80 | 90,000 |
Ordering Materials | 17 | 200 | 3,400 |
Machining | 8 | 6,400 | 51,200 |
Receiving | 16 | 360 | 5,760 |
Total Overhead | 150,360 |
Model Y
A. B. C= A*B
Particulars | Activity Allocation Rate | Activity Capacity for Model X | Total Overhead |
Setting up Equipment | 1,125 | 40 | 45,000 |
Ordering Materials | 17 | 400 | 6,800 |
Machining | 8 | 4,800 | 38,400 |
Receiving | 16 | 720 | 11,520 |
Total Overhead | 101,720 |
Requirement 2
Ordering Materials = $ 10,200
Ratio of Setting up Equipment to Machining = 135,000:89,600
Ordering Materials Cost allocated to Setting up Equipment = 10,200 * 135,000 / 224,600
Ordering Materials Cost allocated to Setting up Equipment = $ 6,131
Ordering Materials Cost allocated to Machining = 10,200 * 89,600 / 224,600
Ordering Materials Cost allocated to Machining = $ 4,069
Receiving Costs = $ 17,280
Ratio of Setting up Equipment to Machining = 135,000 : 89,600
Receiving Costs allocated to Setting up Equipment = 17,280 * 135,000 / 224,600
Receiving Costs allocated to Setting up Equipment = $ 10,386
Receiving Costs allocated to Machining = 17,280 * 89,600 / 224,600
Receiving Costs allocated to Machining = $ 6,894
Main Work
Total Setting up Costs after allocation = 135,000 + 6,131 + 10,386 = $ 151,517
Total Machining Costs after Allocation = 89,600 + 4,069 + 6,894 = $ 100,563
A. B. C= A/B
Particulars | Expected Cost | Activity Capacity | Activity Allocation Rate | |
Setting up Equipment | 151,517 | 120 | 1,262.64 | per Setup |
Machining | 100,563 | 11,200 | 8.98 | per Machine Hour |
For Model X
For Total Amount = Activity Allocation Rate * Activity Capacity
Particulars | Activity Allocation Rate | Activity Capacity | Total Amount |
Setting up Equipment | 1,262.64 | 80 | 101,011 |
Machining | 8.98 | 6400 | 57,465 |
Total Overhead | 158,476 |
For Model Y
Particulars | Activity Allocation Rate | Activity Capacity | Total Amount |
Setting up Equipment | 1,262.64 | 40 | 50,506 |
Machining | 8.98 | 4,800 | 43,098 |
Total Overhead |
93,604 |
Question 3
Overhead Cost of Model X as per ABC = $ 150,360
Overhead Cost of Model X as per Question 2 = $
Cost = 158,476
Change in Overhead Cost = 158,476 - 150,360 = $ 8,116
Percentage Error = Change / Overhead Cost as per ABC * 100
Percentage Error = 8,116 / 150,360 * 100 = 5.40%
For Model Y
Overhead Cost of Model Y as per ABC = $ 101,720
Overhead Cost of Model Y as per Question 2 = $
Cost = 93,604
Change in Overhead Cost = 93,604 - 101,720= $ 8,116
Percentage Error = Change / Overhead Cost as per ABC * 100
Percentage Error = (8,116) / 101,720 * 100 = (7.98%)
eBook Calculator Print Item Silven Company has identified the following overhead activities, costs, and activity drivers...
Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $141,000 Number of setups 120 Ordering materials 24,000 Number of orders 1,200 Machining 105,000 Machine hours 8,750 Receiving 26,280 Receiving hours 1,095 Silven produces two models of cell phones with the following expected activity demands: Model Y Model X X 4,200 8,400 Units completed Number of setups 80 40 400 800 Number of orders...
Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $129,000 Number of setups 120 Ordering materials 15,300 Number of orders 900 Machining 92,400 Machine hours 11,550 Receiving 16,800 Receiving hours 1,050 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y 5,900 11,800 80 40 300 Units completed Number of setups Number of orders Machine hours...
Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $135,000 Number of setups 120 Ordering materials 10,800 Number of orders 600 Machining 119,000 Machine hours 11,900 Receiving 19,200 Receiving hours 960 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 4,300 8,600 Number...
Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $129,000 Number of setups 120 Ordering materials 15,300 Number of orders 900 Machining 92,400 Machine hours 11,550 Receiving 16,800 Receiving hours 1,050 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 5,900 11,800 Number of setups 80 40 Number of orders...
custom products. VE 2 Exercise 4.22 Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment S126,000 Number of setups 150 Ordering materials 18,000 Number of orders 900 Machining 126,000 Machine hours Receiving 30,000 Receiving hours 1,250 10.500 Silven produces two models of cell phones with the following expected activity demands: Model X 5,000 Model Y 10,000 100 Units completed Number...
Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $132,000 Number of setups 120 Ordering materials 27,600 Number of orders 1,200 Machining 118,300 Machine hours 9,100 Receiving 34,320 Receiving hours 1,320 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 5,900 11,800 Number of setups 80 40 Number of orders 400 800 Machine hours 5,200 3,900 Receiving hours 440 880 1. Determine...
Approximately Relevant ABCSilven Company has identified the following overhead activities, costs, and activity drivers for the coming year:Silven produces two models of cell phones with the following expected activity demands:Required:1. Determine the total overhead assigned to each product using the four activity drivers.2. Determine the total overhead assigned to each model using the two most expensive activities. The costs of the two relatively inexpensive activities are allocated to the two expensive activities in proportion to their costs.3. Using ABC as...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $469,800 Number of setups 580 Ordering costs 348,000 Number of orders 17,400 Machine costs 747,000 Machine hours 41,500 Receiving 462,000 Receiving hours 10,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $779,000 Direct labor $471,000 $484,000 Units completed 15,600 7,200...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $480,850 Number of setups 590 Ordering costs 425,500 Number of orders 18,500 Machine costs 700,400 Machine hours 41,200 Receiving 298,800 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $570,000 $821,000 Direct labor $462,000 $472,000 Units completed 16,500 8,800...
Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $492,660 Number of setups 630 Ordering costs 361,200 Number of orders 17,200 Machine costs 882,000 Machine hours 42,000 Receiving 399,000 Receiving hours 9,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $599,000 $ 780,000...