On January 1, 2021, the Marjlee Company began construction of an
office building to be used as its corporate headquarters. The
building was completed early in 2022. Construction expenditures for
2021, which were incurred evenly throughout the year, totaled
$7,200,000. Marjlee had the following debt obligations which were
outstanding during all of 2021:
Construction loan, 10% | $ | 1,800,000 | |
Long-term note, 9% | 2,400,000 | ||
Long-term note, 6% | 4,800,000 | ||
Required:
Calculate the amount of interest capitalized in 2021 for the
building using the specific interest method.
Answer:
Step 1: Figure out your average cost of borrowing = (24,00,000*0.09 + 48,00,000*0.06)/72,00,000 = 7% |
Step 2: Figure out average expenditure during year = $72,00,000/2 = $36,00,000 |
Step 3: Capitalized interest first eats up the specific construction loan so you had 10%*18,00,000 = $180,000 |
Then the next 18,00,000 is at the average borrowing rate = 7%*18,00,000 = $126,000 |
Total capitalized interest = $306,000 |
On January 1, 2021, the Marjlee Company began construction of anoffice building to be used...
On January 1, 2021, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2022. Construction expenditures for 2021, which were incurred evenly throughout the year, totaled $9,600,000. Marjlee had the following debt obligations which were outstanding during all of 2021: Construction loan, 98 Long-term note, 88 Long-term note, 58 $2,400,000 3,200,000 6,400,000 Required: Calculate the amount of interest capitalized in 2021 for the building using the specific...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 115 Long-term note, 105 Long-term note, 71 $1,800,000 2,100,000 4,800,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the specific...
On January 1, 2021, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2022. Construction expenditures for 2021, which were incurred evenly throughout the year, totaled $8,700,000. Marjlee had the following debt obligations which were outstanding during all of 2021: Construction loan, 9% $ 2,175,000 Long-term note, 8% 2,900,000 Long-term note, 5% 5,800,000 Required: Calculate the amount of interest capitalized in 2021 for the building using the...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $5,400,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 12% $ 1,350,000 Long-term note, 11% 1,800,000 Long-term note, 8% 3,600,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $9,000,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 11% $ 2,250,000 Long-term note, 10% 3,000,000 Long-term note, 7% 6,000,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
Exercise 10-22 Interest capitalization (LO10-7] On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018 Construction loan, 116 Long-term note, 101 Long-term note, 73 $1.300.000 2.400,000 4.500.000 Required: Calculate the amount of interest capitalized in 2018 for...
Exercise 10-22 Interest capitalization [LO10-7] On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $5,400,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 12% $ 1,350,000 Long-term note, 11% 1,800,000 Long-term note, 8% 3,600,000 Required: Calculate the amount of interest capitalized in 2018...
On January 1, 2021, the Marlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2022. Construction expenditures for 2021, which were incurred evenly throughout the year, totaled 55.100.000 Mawjee had the following debt obligations which were outstanding during all of 2020 Construction loan, 135 Longteremte, 125 Long-tere note, 1,275,000 1.700,000 Required: Calculate the amount of interest capitalized in 2021 for the building using the specific terest method
On January 1, year 1, the Maxlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in year 2. Construction expenditures for year 1, which were incurred evenly throughout the year, totaled $5,000,000. Maxlee had the following debt obligations which were outstanding during all of year 1: Construction loan, 10% $1,660,000 Long-term note, 9% 2,500,000 Long-term note, 6% 5,000,000 Required: Calculate the amount of interest capitalized in year 1 for...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 $2,050,000 1,800,000 2,000,000 1,800,000 450,000 783,000 1,080,000 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the company obtained a $5,000,000 construction loan with a 9% interest rate. The...