Question

Implementing plans in the planning and control cycle relates to the act of: planning managing controlling....

Implementing plans in the planning and control cycle relates to the act of:

planning

managing

  • controlling.

  • revising plans.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Implementing Plans in the planning and control cycle relates to the act of managing.

Other options are incorrect because in the planning stage we establish objectives and develop our action plans rather than implementing them. While in the controlling stage we do performance evaluation and check how effective was the process.Further during revision of plans we take corrective action against plans which were not effective and revise them accordingly.

Add a comment
Know the answer?
Add Answer to:
Implementing plans in the planning and control cycle relates to the act of: planning managing controlling....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT