Question

The third phase of the project life cycle has two parts: detailed planning and implementing the plan. brainstorming and detai
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:

Contracting and performing the project.

Reason: as per the Project Life Cycle the third phase is Performing. In which we will lead the project plan and execute it and implement it as per plan for that we do contracts with related chains and do the performing.

Add a comment
Know the answer?
Add Answer to:
The third phase of the project life cycle has two parts: detailed planning and implementing the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The baseline plan is set at the conclusion of the project life cycle phase. Performing Initiating...

    The baseline plan is set at the conclusion of the project life cycle phase. Performing Initiating Planning Closing adds a unique dimension to managing projects as it changes the dynamics of a project. It can adversely affect the project outcome if the project participants are not aware of cultural differences and multinational economic transactions. Customer interaction Diversity Customer satisfaction Globalization

  • Question One Explain the difference between project life cycle and product life cycle? Question Two Alpha...

    Question One Explain the difference between project life cycle and product life cycle? Question Two Alpha Project Managers believe that “Spending more time on planning should pay off in execution” Illustrates your answer with a daily life example? Question Three SWOT analysis—analyzing Strengths, Weaknesses, Opportunities, and Threats—which is one tool used in strategic planning. Suppose, a group of people wants to start a new business in the film industry to identify potential projects. You are required to perform SWOT analysis...

  • An important task to complete during the closing phase of the project life cycle is complete...

    An important task to complete during the closing phase of the project life cycle is complete any unfinished tasks for the project. evaluate the performance of the project. manage communications with the stakeholders of the project. secure another contract with the project sponsor.

  • Review Questions 1. This phase in the project life cycle includes clear objectives, importance of the...

    Review Questions 1. This phase in the project life cycle includes clear objectives, importance of the project, and the expected outcome on the organization. a. Initiation b. Planning c. Execution d. Closure 2. A PI team in the radiology department determined that the wait time for procedures in their depart- ment is too long. This team worked through the steps in the PI process, developed a project and timeline, collected data, and made a recommendation to improve the wait times....

  • A plant life-cycle consists of two multi-cellular phases known as the ___________. The diploid phase is...

    A plant life-cycle consists of two multi-cellular phases known as the ___________. The diploid phase is known as the _____ _____, and the haploid phase is known as the _________. In bryophytes the _________ is the dominant generation, which is different from lycophytes and pteridophytes. Spores are produced via _________ to enter the haploid generation, and __________ produces a zygote to enter the diploid generation.

  • Complete the following table that focuses on Family Life Cycle Phases. Family Life Cycle Phase       Key Principles of E...

    Complete the following table that focuses on Family Life Cycle Phases. Family Life Cycle Phase       Key Principles of Emotional Process of Transition         Second-Order Changes Required to Proceed Developmentally Emerging Young Adults Newly Married Couples Families with Young Children Families with Adolescents Middle Aged families dealing with retirement Families dealing End of Life Issues Reflection Questions: After completing the tables, explain the possible cultural factors that play a major role in how families transition through the life cycle. (150-200 words) Select...

  • Part I: Basic Concepts Q1A- Fill in the blank: i-The project life cycle typically passes sequentially...

    Part I: Basic Concepts Q1A- Fill in the blank: i-The project life cycle typically passes sequentially ycle typically passes sequentially through four stages: (2 mark) ii-The Conceptualization Phase typically involves:(1 mark) 01B- Multiples Your compar of your con Circle the 1. ALL iii-The Termination Phase typically involves: (1 mark) iv.... design, construction, testing, and support after they are defined. This model is used restricted after the requirements are defined. and support. This life cycle model assumes that requirements will remain...

  • Which of the following is NOT a main phase of the software development life cycle? Testing...

    Which of the following is NOT a main phase of the software development life cycle? Testing Prototyping System design Implementation The agile software development methodology is categorized by all of the following, EXCEPT: Collaboration between both developers and clients Incremental changes with a focus on quality and attention to detail Heavy emphasis on developer decision-making Heavy reliance on client input A Project Manager does all of the following tasks, EXCEPT __________. coordinating schedules and resources to maximize the output of...

  • A ball bearing on a shaft has a variable loading as shown in the table below. What is the minimum C10 rating required for the bearing to last 10,000 hours for Ls Life? One Cycle Phase 2 6 1500 2000 1...

    A ball bearing on a shaft has a variable loading as shown in the table below. What is the minimum C10 rating required for the bearing to last 10,000 hours for Ls Life? One Cycle Phase 2 6 1500 2000 1.8 Phase 1 4 1000 Phase 3 Minutes in Phase Speed (RPM) Bearing Load (N)3000 Application Factor 800 5000 1.5 1.2 A ball bearing on a shaft has a variable loading as shown in the table below. What is the...

  • Enterprise Group Policy Application Gigantic Life Insurance is planning to implement Group Policy to control user...

    Enterprise Group Policy Application Gigantic Life Insurance is planning to implement Group Policy to control user desktops. Some ofthe desired settings are to be implemented for the entire organization, while other settings apply only to particular regions or departments. Gigantic Life Insurance is organized as a single domain. The network manager is concerned that dividing into multiple domains to apply individual Group Policies will be a lot of work and disrupt users. Explain why this is not a concern.Case 13-2:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT