Question

Using the values provided in Table 21-1, minimum sewage elevation in interceptor of 112.60 m, maximum sewage elevation in interceptor of 112.80 m, discharge elevation to stilling well of 116.40 m, an average design flow of 8,600 m3/d, peaking factor for peak hour of 2.8 and minimum factor of 0.49.

A. Determine the most efficient screw pump diameter (in m)
B. How many flights are recommended
C. How many pumps are recommended in the final design?

Typical/comment TABLE 21-1 Typical design criteria for primary sedimentation basins Parameter Range of values General Overflo


TABLE 21-1 (continued) Typical design criteria for primary sedimentation basins Parameter Range of values Typical/comment Baf

0 0
Add a comment Improve this question Transcribed image text
Answer #1

max. height the strene pump must lift = Discharge elevation - min. Sewage elevation = 116.40 – 112-6 - 3-87 Mini an flow rateMin. flow rate - 4214 m3/d 24 hoold = 175-58 m3/h Aug. flow rate = 8600 wild . 24 h/dy = 358:33 m3/15 peak for flow rate = 24- The dia of Pump j 1.07m, no. of flisnts are le no. of Pumps are 3 ... Cone Puup out of Sesnice)

Add a comment
Know the answer?
Add Answer to:
Using the values provided in Table 21-1, minimum sewage elevation in interceptor of 112.60 m, maximum...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Water and Wastewater Treatment SP-WATER TREATMENT PLANT SEDIMENTATION BASIN Design a rectangular, horizontal flow sedimentation process...

    Water and Wastewater Treatment SP-WATER TREATMENT PLANT SEDIMENTATION BASIN Design a rectangular, horizontal flow sedimentation process for a water treatment plant for turbidity removal Design Maximum Day Flow-20,000 m2ld Two parallel sedimentation tank, each designed for half of the total flow Depth 4.5 m, Width 6 m, Surface Overflow Rate 50 m/day Chain and flight sludge collector will be used, hence the limiting width of 6 m. Minimum Hydraulic Retention Time (detention time) 2 hrs Maximum weir rate 250 m/day/m...

  • A water treatment plant is processing water at a flow rate of 1.5 m/s using three parallel treatm...

    A water treatment plant is processing water at a flow rate of 1.5 m/s using three parallel treatment trains. The detention times for the rapid mix tank, flocculation basin, and rectangular sedimentation basin are 10 sec, 30 min and 60 min, respectively. The velocity gradients for the rapid mix and flocculation tanks are 900 s and 60:40:20 s1, respectively. The viscosity of water is 0.001 Pa-s. (a) Determine the size and power requirements for rapid mix tanks. (b) Determine the...

  • Any tips or pointers? characteristics: Maximum daily flow 3 ms Average daily flow 2 m'/s Coagulant...

    Any tips or pointers? characteristics: Maximum daily flow 3 ms Average daily flow 2 m'/s Coagulant Ferric chloride Overflow Rate 3.1 m/m2h It is needed to specify the number of sedimentation basins, the basin dimensions, hydraulic retention time, horizontal velocity and outlet weir loading rate. Assume necessary data. The following items are suggested to be in your design report Title page: Design Problem title, your name, date, etc... Abstract: Contains objective statement, summarize the ma Introduction: Introducing the problem subject...

  • QUESTION 4 horizontal flow grit chamber with rectangular x-section for treating maximum sewage flow of 10 MIld. Assu...

    QUESTION 4 horizontal flow grit chamber with rectangular x-section for treating maximum sewage flow of 10 MIld. Assume the particles settling velocity is 2.4 cm/sec, B is 0.06, fis 0.03 and particles diameter (D) is 0.02 cm. Also, take width of chamber as 1.0 m, free board as 0.3 m, grit accumulation depth as 0.25 m, specific gravity (SG) of particles as 2.65 and 2 [30] Design a mextra length for inlet and outlet works. QUESTION 4 horizontal flow grit...

  • 1.A rectangular settling basin with a length to widith rato of 3:1 receives a flow of...

    1.A rectangular settling basin with a length to widith rato of 3:1 receives a flow of 850000 l/d the basin depth is 4 m and the detention time of water in the tank is 144minutes (I)what are the surface overflow rate and horizontal velocity if the is distributed uniformly across the cross sectional area of the tank (II) Calculate the weir loading rate if the leght is 2 times the basin widith 2.Design a set of three rapid sand filters...

  • A wastewater treatment plant that treats wastewater to secondary treatment standards uses a primary sedimentation process...

    A wastewater treatment plant that treats wastewater to secondary treatment standards uses a primary sedimentation process followed by conventional activated sludge process composed of covered aeration tanks and secondary clarifiers. You are asked to calculate the different operation parameters to make sure that the system is operated within normal process ranges listed in the reference tables below. Table 5-20 Typical design information for primary sedimentation tanks U.S. customary units Item Unit Range Typical Primary sedimentation tanks followed by secondary treatment...

  • summarizr the followung info and write them in your own words and break them into different...

    summarizr the followung info and write them in your own words and break them into different key points.   6.5 Metering Chamber: 6.5.1 The minimum size of the metering box is governed by the metering area required to obtain a representative test area for the specimen (see 7.2) and for maintenance of reasonable test accuracy. For example, for specimens incorporating air spaces or stud spaces, the metering area shall span an integral number of spaces (see 5.5). The depth of...

  • summatize the following info and break them into differeng key points. write them in yojr own...

    summatize the following info and break them into differeng key points. write them in yojr own words   apartus 6.1 Introduction—The design of a successful hot box appa- ratus is influenced by many factors. Before beginning the design of an apparatus meeting this standard, the designer shall review the discussion on the limitations and accuracy, Section 13, discussions of the energy flows in a hot box, Annex A2, the metering box wall loss flow, Annex A3, and flanking loss, Annex...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT