Question

CPM -5% A Subcontractor must do the following: a) Framing (5 days) b) Drywall Installation (4 days) c) Drywall finish and pai

0 0
Add a comment Improve this question Transcribed image text
Answer #1

first activity should be framing and one can not start draywall installation without completing framing work.the next task is finishing and painting. we can carry both installtion and finishing and painting as parallel task by giving one day or two day break for the last event to ensure some part of the preceding activity will be completed so that the next task can be started

start) days framing B 4 days Drymour installation ing days work 3 days (finishing and painting of Dry wall)the above shown logical network is built by CPM method of project planning.

in the above network 2 days have been left with no work to ensure some part of installation of drywall to be completed to carry finishing works and also to satisfy the given condition "each activity should be finished atleast 1 day after finishing of its predecessor activity".

in the above network critical path has been shown with black line.the network is telling that after framing activity, installation, finishing amd painting of the drywall are carried as parallel activities to reduce project duration.

Therefore from the above network the total project duration is 10 days.(critical path duration)

Add a comment
Know the answer?
Add Answer to:
CPM -5% A Subcontractor must do the following: a) Framing (5 days) b) Drywall Installation (4...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Must use AOA PERT/CPM Manual Calculations and show Networks. 10. A farm owner is going to...

    Must use AOA PERT/CPM Manual Calculations and show Networks. 10. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Activity Activity Description Predecessor Time Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building b.c,d Paint finish Η Check out facility Construct the network for this project and calculate the...

  • Construction methods Do 4-3 5. Answer the following two questions, 5-1 and S-2 5-1) Draw the...

    Construction methods Do 4-3 5. Answer the following two questions, 5-1 and S-2 5-1) Draw the "node" network diagram and perform the CPM calculations based on the end-of-day convention to complete the table entries. (20 points) (Note: use very simple node design for the network diagram: for example, box or circle.) Activity! Duration | Predecessors | EST E-LS 1 LF- B. BFF/2 | 구 | 11 | 15 | 19 E, F SS12 5 13 it is assumed that the...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT