I need help with requirements 2 and 3, please. Thank you!
1) | ||||||
Trudell Corporation | ||||||
Total Budgeted Indirect Manufacturing Costs | ||||||
Activity | Budgeted Quantity of Cost Allocation Base | Activity Cost Allocation Rate | Total Budgeted Indirect Cost | |||
Materials handling = (6 × 1,000) + (8 × 1,000) | 14000 | $3.50 | $49,000.00 | |||
Machine setups = (10+10) | 20 | $450.00 | $9,000.00 | |||
Insertion of parts = (6 × 1,000) + (8 × 1,000) | 14000 | $30.00 | $420,000.00 | |||
Finishing =(1 x 1000) + (3 x 1000) | 4000 | $53.00 | $212,000.00 | |||
Total budgeted indirect cost | $690,000.00 | |||||
2) | ||||||
Trudell Corporation | ||||||
ABC Indirect Manufacturing Cost per Unit | ||||||
Activity | Cost Allocation Rate | Quantity of Cost Allocation Base Used By: | Allocated Activity Cost Per Wheel | |||
Standard | Deluxe | Standard | Deluxe | |||
Materials handling | $3.50 | 6 | 8 | $21.00 | $28.00 | |
Machine setups = 10/1000 | $450.00 | 0.01 | 0.01 | $4.50 | $4.50 | |
Insertion of parts | $30.00 | 6 | 8 | $180.00 | $240.00 | |
Finishing | $53.00 | 1 | 3 | $53.00 | $159.00 | |
Total ABC allocated indirect cost | $258.50 | $431.50 | ||||
3) | ||||||
Budgeted total manufacturing overhead (a) | $690,000.00 | (Part 1) | ||||
Budgeted total direct labor hours= (1,000 × 2.7) + (1,000 × 3.3) (b) | 6000 | |||||
Plant-wide overhead allocation = (a)/(b) | $115.00 | per direct labor hour | ||||
Manufacturing overhead cost per wheel: | ||||||
Standard = 2.7 x $115 | $310.50 | |||||
Deluxe = 3.3 x $115 | $368.00 | |||||
I need help with requirements 2 and 3, please. Thank you! Several years after reengineering its...
Several years after reengineering its production process, King Corporation hired a new controller, Rachael Johnson. (Click the icon to view additional information.) The number of parts is now a feasible allocation base because King recently installed a plantwide computer system. King produces two wheel models: Standard and Deluxe. Budgeted data for the upcoming year are as follows: (Click the icon to view the additional data.) For the upcoming year, King's budgeted ABC manufacturing overhead allocation rates are as follows: (Click...
Several years after reengineering its production process, Zeke Corporation hired a new controller, Barb Joe. a (Click the icon to view additional information.) The number of parts is now a feasible allocation base because Zeke recently installed a plantwide computer system. Zeke produces two wheel models: Standard and Deluxe. Budgeted data for the upcoming year are as follows: (Click the icon to view the additional data.) For the upcoming year, Zeke's budgeted ABC manufacturing overhead allocation rates are as follows:...
Several years after reengineering its production process, Zeke Corporation hired a new controller, Barb Joe. (Click the icon to view additional information.) The number of parts is now a feasible allocation base because Zeke recently installed a plantwide computer system. Zeke produces two wheel models: Standard and Deluxe. Budgeted data for the upcoming year are as follows: (Click the icon to view the additional data.) For the upcoming year, Zeke's budgeted ABC manufacturing overhead allocation rates are as follows: -...
Several years after reengineering its production process, Kane Corporation hired a new controller, Christine Erickson. i (Click the icon to view additional information.) For the upcoming year, Kane's budgeted ABC manufacturing overhead allocation rates are as follows: BE: (Click the icon to view the additional data.) 0 X - More Info She developed an ABC system very similar to the one used by Kane's chief rival. Part of the reason Erickson developed the ABC system was because Kane's profits had...
11. Several years after reengineering its production process, Zippy Corporation hired a new controller. Denise French (Click the icon to view additional information.) For the upcoming year, Zippy's budgeted ABC manufacturing overhead allocation rates are as follows: 2(Click the icon to view the additional data.) The number of parts is now a feasible allocation base because Zippy recently installed a plantwide computer system. Zippy produces two wheel models: Standard and Deluxe. Budgeted data for the upcoming year are as follows:...
Several years after reengineering its production process, King Corporation hired a The number of parts is now a feasible allocation base because King recently installed new controller, Alice Brown. a plantwide computer system. King produces two wheel models: Standard and (Click the icon to view additional information.) Deluxe. Budgeted data for the upcoming year are as follows: (Click the loon to view the additional data.) For the upcoming year, King's budgeted ABC manufacturing overhead allocation rates are as follows: (Click...
Several years after reengineering its production process, Biltmore Corporation hired a new controller, Tammy English. (Click the icon to view additional information.) The number of parts is now a feasible allocation base because Biltmore recently installed a plantwide computer system. Biltmore produces two wheel models: Stan (Click the icon to view the additional d A Data Table For the upcoming year, Biltmore's budgeted ABC manufacturing overhead allocation rates are as follows: E: (Click the icon to view the additional data.)...
Several years after reengineering is production process. Trudell Corporation hired a new controller Ashley Adams (Click the icon to view additional Information) For the upcoming your, Trudel's budgeted ABC manufacturing overhead allocation rates are as follows: m (Click the icon to view the additional data.) The number of parts is now a feasible allocation base because Trudell recently installed a planwide computer stem. Trudel produces to wheel models. Standard and Deluxe Budgeted data for the upcoming year are as follows:...
Several years after reengineering its production process,
Biltmore Corporation hired a new controller, Tammy English. For
the upcoming year, Biltmore's budgeted ABC manufacturing overhead
allocation rates are as follows:
The number of parts is now a feasible allocation base because
Biltmore recently installed a plantwide computer system. Biltmore
produces two wheel models: Standard and Deluxe. Budgeted data for
the upcoming year are as follows:
Requirement 1. Compute the total budgeted manufacturing overhead
cost for the upcoming year.
Requirement 2....
Question Help X E4-25A (similar to) Several years after reengineering its production process. Batore Corporation hired a new controle Tammy English Click the icon to win mon) For the upcoming year, Bitmone's budgeted ABC manufacturing overhead location rates are as follows: Click the icon to view the additional data The number of parts is now a feasible allocation base because more recently installed a plantvide computer system Biltmore produces two wheel moes Standard and Dele Budgeted data for the upcoming...