1 Actual manufacturing overhead cost incurred
2
a b c=a/b (round 1 decimal place)
Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Cost per activity
Labor-related Direct labor-hours 585000 45000 DLHs 13
Purchase orders Number of orders 50,160 1520 orders 33
Parts management Number of part types 3,57,000 399 part types 894.7
Board etching Number of boards 4,51,000 1980 boards 227.8
General factory Machine-hours 6,93,600 81600 MHs 8.5
Activity Cost Pool Activity rate Actual activity
Labor-related 13 DLHs
Purchase orders 33 orders
Parts management 894.7 part types
Board etching 227.8 boards
General factory 8.5 MHs
3
Actual activity b c=a*b
Activity Cost Pool Actual activity Activity rate Applied overhead
Labor-related 40500 13 526500
Purchase orders 1290 33 42570
Parts management 420 894.7 375774
Board etching 2180 227.8 496604
General factory 82100 8.5 697850
Total 2139298
4
Actual overhead applied 2139298
Actual manufacturing overhead cost incurred 2318000
Underapplied overhead cost -178702
178702
Hi mate,
I would be grateful to you if you can provide a thumbs up and write one beautiful comment. It will improve my rating and let me continue my journey here.
In case of doubt, please comment. I will consider myself fortunate if I can help you.
All the best for your bright future.
Add a comment
Know the answer?
Add Answer to:
Sylvan Company uses activity-based costing to determine product costs for external financial reports. Some of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sylvan Company uses activity-based costing to determine product costs for external finaleial reports. Some of the...

    Sylvan Company uses activity-based costing to determine product costs for external finaleial reports. Some of the entries have been completed to the manufacturing overhead account for the current year, as shown by entry (a) below: Manufacturing Overhead (a) 2,401,000 Required: 1. What does entry (a) represent? O Actual manufacturing overhead cost incurred O Overhead applied O Machine-hours 2. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools:...

  • Sorie Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sorie Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 231,600 38,600 DLHs Purchase orders Number of orders $ 15,015 231 orders Parts management Number of part types $ 95,200 112 part types Board etching Number of boards $ 106,800 1,780 boards General factory Machine-hours $ 184,500...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHS 221 orders 99 part types 1,820 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Expected Measure Overhead Expected Activity Cost Pool Cost Activity Labor-related Direct labor-hours $380,000 38.000 DLHS Purchase orders Number of orders $11.935 217 orders Parts Number of part $ 79,500 1 06 part types management types Board etching Number of boards $93.000 1,860 boards General factory Machine-hours $240,500 18.500 MHS Required:...

  • Sultan Company uses an activity-based costing system At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Expected Measure Overhead Expected Activity Cost Pool Cost Activity Labor-related Direct labor-hours $ 148,000 29,600 DLHs Purchase orders Number of orders $ 15,180 253 orders Parts management Number of part types $ 85,680 102 part types Board etching General factory Number of boards Machine-hours $ 99,550 $ 162,400 1,810 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHS 221 orders 99 part types 1,820 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools Activity Measure Expected Overhead Expected Activity Activity Cost Pool Labor-related Purchase orders Parts management Cost Direct labor-hours Number of orders Number of part types S 284,000 35,500 DLHs $ 6,790 S 194 orders 71,340 82 part types Number of boards Machine-hours S 57,900 $ 229,900 20,900 MH:s 1,930 boards Board etching...

  • Sultan Company uses an activity-based costing system.         At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system.         At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for Its five activity cost pools: Activity Measure Expected Overhead Expected Activity DLHS Activity Cost Pool Cost 135,600 24 Labor-related Direct labor-hours 22,600 $ 8,400 $ 68,870 240...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 231,600 $ 15,015 $ 95,200 $ 106,800 $ 184,500 Expected Activity 38,600 DLHS 231 orders 112 part types 1,780 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHs 221 orders 99 part types 1,820 boards...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT