Question

Profit-Linked Productivity Measurement In 20x2, Choctaw Company implements a new process affecting labor and materials. Choctaw...

Profit-Linked Productivity Measurement

In 20x2, Choctaw Company implements a new process affecting labor and materials.

Choctaw Company provides the following information so that total productivity can be valued:

20x1 20x2
Number of units produced 570,000 480,000
Labor hours used 190,000 240,000
Materials used (lbs.) 2,850,000 1,600,000
Unit selling price $23 $25
Wages per labor hour $15 $17
Cost per pound of material $3.40 $3.50

Required:

1. Calculate the cost of inputs in 20x2, assuming no productivity change from 20x1 to 20x2. If required, round your answers to the nearest dollar.

Cost of labor $
Cost of materials   
Total PQ cost $

2. Calculate the actual cost of inputs for 20x2. If required, round your answers to the nearest dollar.

Cost of labor $
Cost of materials   
Total current cost $

What is the net value of the productivity changes? If required, round your answers to the nearest dollar.
$

How much profit change is attributable to each input's productivity change? If an item is negative, use a minus (-) sign to indicate.

Labor productivity change $
Materials productivity change $

3. What if a manager wants to know how much of the total profit change from 20x1 to 20x2 is attributable to price recovery? Calculate the total profit change.
$

Calculate the price-recovery component.

$

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Profit-Linked Productivity Measurement In 20x2, Choctaw Company implements a new process affecting labor and materials. Choctaw...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cornerstone Exercise 15.4 (Algorithmic) Profit-Linked Productivity Measurement In 2015, Choctaw Company implements a new process affecting...

    Cornerstone Exercise 15.4 (Algorithmic) Profit-Linked Productivity Measurement In 2015, Choctaw Company implements a new process affecting labor and materials. Choctaw Company provides the following information so that total productivity can be valued: 2014 2015 Number of units produced 600,000 510,000 Labor hours used 200,000 255,000 Materials used (lbs.) 2,000,000 1,275,000 Unit selling price 24 26 Wages per labor hour 14 16 Cost per pound of material 3.40 3.50 Required: 1. Calculate the cost of inputs in 2015, assuming no productivity...

  • Profile Productivity Measurement Objective In 20x2, Choctaw Company implements a new process affecting labor and materials....

    Profile Productivity Measurement Objective In 20x2, Choctaw Company implements a new process affecting labor and materials. The following reported data are provided to evaluate the effect on the company’s productivity: 20x1 20x2 Number of units produced 510,000 360,000 Labor hours used 127,500 72,000 Materials used (lbs.) 1,457,143 900,000 Required: 1. Calculate the productivity profile for 20x1. If required, round your answers to two decimal places. Partial Operational Productivity Ratios 20x1 Profile Labor productivity ratio Material productivity ratio 2. Calculate the...

  • Profile Productivity Measurement Objective In 20x2, Choctaw Company implements a new process affecting labor and materials. The following reported data are provided to evaluate the effect on the compa...

    Profile Productivity Measurement Objective In 20x2, Choctaw Company implements a new process affecting labor and materials. The following reported data are provided to evaluate the effect on the company’s productivity: 20x1 20x2 Number of units produced 600,000 450,000 Labor hours used 150,000 90,000 Materials used (lbs.) 1,333,333 900,000 Required: 1. Calculate the productivity profile for 20x1. If required, round your answers to two decimal places. Partial Operational Productivity Ratios 20x1 Profile Labor productivity ratio Material productivity ratio 2. Calculate the...

  • Profile Productivity Measurement Objective In 2015, Choctaw Company implements a new process affecting labor and materials....

    Profile Productivity Measurement Objective In 2015, Choctaw Company implements a new process affecting labor and materials. The following reported data are provided to evaluate the effect on the company’s productivity: 2014 2015 Number of units produced 600,000 450,000 Labor hours used 200,000 112,500 Materials used (lbs.) 2,000,000 1,285,714 Required: 1. Calculate the productivity profile for 2014. If required, round your answers to two decimal places. Partial Operational Productivity Ratios 2014 Profile Labor productivity ratio Material productivity ratio 2. Calculate the...

  • Interperiod Measurement of Productivity, Profit-Linked Measurement Helena Company needs to increase its profits and so h...

    Interperiod Measurement of Productivity, Profit-Linked Measurement Helena Company needs to increase its profits and so has embarked on a program to increase its overall productivity. After one year of operation, Kent Olson, manager of the Columbus plant, reported the following results for the base period and its most recent year of operations: 20x1 20x2 Output 185,100      217,200      Power (quantity used) 18,510      11,200      Materials (quantity used) 46,275      47,800      Suppose the following input prices are provided for each year: 20x1 20x2 Unit...

  • Productivity Measurement, Technical and Allocative Efficiency, Partial Measures Carsen Company produces handcrafted pottery that uses two...

    Productivity Measurement, Technical and Allocative Efficiency, Partial Measures Carsen Company produces handcrafted pottery that uses two inputs: materials and labor. During the past quarter, 20,000 units were produced, requiring 80,000 pounds of materials and 40,000 hours of labor. An engineering efficiency study commissioned by the local university revealed that Carsen can produce the same 20.000 units of output using either of the following two combinations of Inputs: Combinations: Materials 70,000 $4,600 Labor 38,000 33,500 The cost of materials is $10...

  • Direct Materials and Direct Labor Variance Analysis Shasta Fixture Company manufactures faucets in a small manufacturing...

    Direct Materials and Direct Labor Variance Analysis Shasta Fixture Company manufactures faucets in a small manufacturing facility. The faucets are made from brass. Manufacturing has 30 employees. Each employee presently provides 35 hours of labor per week. Information about a production week is as follows: Standard wage per hour $13.20 Standard labor time per unit 20 min. Standard number of lbs. of brass 1.3 lbs. Standard price per Ib. of brass $12.25 Actual price per lb. of brass $12.50 12,051...

  • Variable Manufacturing Unit Cost 20x1 Cost 20x2 Cost Rounded to 2 Decimal Places Lamp Kit Labor...

    Variable Manufacturing Unit Cost 20x1 Cost 20x2 Cost Rounded to 2 Decimal Places Lamp Kit Labor Variable Overhead $16 $ 2 $ 2 Projected Percent Increase 2% 2 .50% 2 .50% $16.32 $2.07 $2.05 {4.01) (4.02) (4.03) Projected Variable Manufacturing Cost Per Unit $20.44 (4.04) Total Variable Cost Per Unit 20x1 Cost 20x2 Cost Rounded to 2 Decimal Places Projected Percent Increase 2.00% 6.00% Variable Selling Variable Administrative Projected Variable Manufacturing Unit Cost $3.00 $2.00 3.06 2.121 20.44 {4.05) (4.06)...

  • Direct Materials and Direct Labor Variance Analysis Abbeville Fixture Company manufactures units in a small manufacturing...

    Direct Materials and Direct Labor Variance Analysis Abbeville Fixture Company manufactures units in a small manufacturing facility. The units are made from brass. Manufacturing has 40 employees. Each employee presently provides 35 hours of labor per week. Information about a production week is as follows: Standard wage per hour $15.6 Standard labor time per unit 20 min. Standard number of lbs. of brass 2 lbs. Standard price per lb. of brass $10 Actual price per lb. of brass $10.25 Actual...

  • Direct Materials and Direct Labor Variance Analysis Abbeville Fixture Company manufactures units in a small manufacturing...

    Direct Materials and Direct Labor Variance Analysis Abbeville Fixture Company manufactures units in a small manufacturing facility. The units are made from brass. Manufacturing has 30 employees. Each employee presently provides 35 hours of labor per week. Information about a production week is as follows: $16.2 Standard wage per hour Standard labor time per unit Standard number of lbs. of brass 10 min. 2.1 lbs. $12 Standard price per lb. of brass Actual price per lb. of brass Actual lbs....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT