A manufacturing company has a small production line dedicated to the production of a particular product. The line has four st
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question: A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the finished product. Station 1 can process 2,700 units per month, station 2 can process 2,200/month, station 3 can process 2,000/month, and station 4 2,100/month.

a. What station sets the maximum possible output from this system?

Answer: Station 3

Explanation:

Given that:

Station 1 = 2700 units per month

Station 2 = 2200 units per month

Station 3 = 2000 units per month

Station 4 = 2100 units per month

Now, the slowest process creates the bottleneck here Station 3 is a slowest process of them all.

Therefore:

The maximum possible output from this system = Station 3

b. What is that maximum output number?

Answer: 2000 units per month

Explanation:

The Station 3 is slowest of them all which attains maximum possible output from this system hence the maximum output number of Station 3 is = 2000 units per month.

Add a comment
Know the answer?
Add Answer to:
A manufacturing company has a small production line dedicated to the production of a particular product....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A production line at V. J. Sugumaran's machine shop has three stations. The first station can...

    A production line at V. J. Sugumaran's machine shop has three stations. The first station can process a unit in 6 minutes. The second station has three identical machines, each of which can process a unit in 15 minutes (each unit only needs to be processed on one of the three machines). The third station can process a unit in 8 minutes ▼| is the bottleneck station, with a bottleneck time of] | minutes per unit (enteryourresponse as a whole...

  • Colt Company owns a machine that can produce two specialized products Production time for Product TLX...

    Colt Company owns a machine that can produce two specialized products Production time for Product TLX is three units per hour and for Product MTV is four units per hour. The machine's capacity is 2,100 hours per year. Both products are sold to a single customer who has agreed to buy all of the company's output up to a maximum of 3,570 units of Product TLX and 4,010 units of Product MTV. Selling prices and variable costs per unit to...

  • 8. A production line has three workstations. At station 1, there is one machine, which takes...

    8. A production line has three workstations. At station 1, there is one machine, which takes 2 minutes to process one unit. The unit then passes to station 2, which has two machines in parallel. The unit must be processed on just one of the machines at station 2, and each machine at station 2 takes 5 minutes to process one unit. The unit then passes to station 3, which has 6 machines in parallel. The unit must be processed...

  • Colt Company owns a machine that can produce two specialized products. Production time for Product TLX...

    Colt Company owns a machine that can produce two specialized products. Production time for Product TLX is two units per hour and for Product MTV is five units per hour. The machine's capacity is 2,100 hours per year. Both products are sold to a single customer who has agreed to buy all of the company's output up to a maximum of 3,570 units of Product TLX and 1,905 units of Product MTV. Selling prices and variable costs per unit to...

  • Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the...

    Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (50 sec.): The plastic tube for the frame is cut to size. Step 2 (40 sec.): The tube is put together. Step 3 (55 sec.): The frame...

  • Briefly describe How we get the Mean transport value? A semi-automated flexible manufacturing cell (FMC) is used to pro...

    Briefly describe How we get the Mean transport value? A semi-automated flexible manufacturing cell (FMC) is used to produce three products The products are made by two automated processing stations followed by an assembly station. There is also a load/unload station. Material handling between stations in the FMC is accomplished by mechanized carts that move tote bins containing the particular components to be processed and then assembled into a given product. The carts transfer tote bins between stations. In this...

  • Colt Company owns a machine that can produce two specialized products. Production time for Product TLX...

    Colt Company owns a machine that can produce two specialized products. Production time for Product TLX is two units per hour and for Product MTV is four units per hour. The machine's capacity is 2,300 hours per year. Both products are sold to a single customer who has agreed to buy all of the company's output up to a maximum of 3,910 units of Product TLX and 1,840 units of Product MTV. Selling prices and variable costs per unit to...

  • Colt Company owns a machine that can produce two specialized products. Production time for Product TLX...

    Colt Company owns a machine that can produce two specialized products. Production time for Product TLX is two units per hour and for Product MTV is five units per hour. The machine's capacity is 2,750 hours per year. Both products are sold to a single customer who has agreed to buy all of the company's output up to a maximum of 4,700 units of Product TLX and 2,500 units of Product MTV. Selling prices and variable costs per unit to...

  • Colt Company owns a machine that can produce two specialized products Production time for Product TLX...

    Colt Company owns a machine that can produce two specialized products Production time for Product TLX is three units per hour and for Product MTV is four units per hour. The machine's capacity is 2.400 hours per year. Both products are sold to a single customer who has agreed to buy all of the company's output up to a maximum of 4,080 units of Product TLX and 4,540 units of Product MTV Selling prices and variable costs per unit to...

  • Colt Company owns a machine that can produce two specialized products. Production time for Product TLX...

    Colt Company owns a machine that can produce two specialized products. Production time for Product TLX is two units per hour and for Product MTV is four units per hour. The machine’s capacity is 2,500 hours per year. Both products are sold to a single customer who has agreed to buy all of the company’s output up to a maximum of 4,250 units of Product TLX and 1,980 units of Product MTV. Selling prices and variable costs per unit to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT