A production line at V. J. Sugumarans machine shop has three stations. The first station can process a unit in 6 minutes. The second station has three identical machines, each of which can process a unit in 15 minutes (each unit only needs to be processed on one of the three machines). The third station can process a unit in 8 minutes ▼| is the bottleneck station, with a bottleneck time of] | minutes per unit (enteryourresponse as a whole number Station 1 Station 3 Station 2

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Station 3 is the bottleneck in this specific process as it would be having a queue for processing as it is taking the longest time as compared to the other two stations.

Station 3

Add a comment
Know the answer?
Add Answer to:
A production line at V. J. Sugumaran's machine shop has three stations. The first station can...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 8. A production line has three workstations. At station 1, there is one machine, which takes...

    8. A production line has three workstations. At station 1, there is one machine, which takes 2 minutes to process one unit. The unit then passes to station 2, which has two machines in parallel. The unit must be processed on just one of the machines at station 2, and each machine at station 2 takes 5 minutes to process one unit. The unit then passes to station 3, which has 6 machines in parallel. The unit must be processed...

  • (20) A flow line has two stations. The first station has a processing time of 6...

    (20) A flow line has two stations. The first station has a processing time of 6 minutes, and it has 3 servers. The second has a processing time of 11 minutes, and it has 4 servers. There is a constant arrival rate of jobs to the line What is the maximum utilization at each station? What assumptions do you need to ensure that maximum utilization is achieved? It turns out that the non-bottleneck station is very expensive, so management would...

  • A work cell has four stations, and each unit produced at the cell needs to be processed by all of the stations in series. (The same unit cannot be worked on by four stations simultaneously.) The capac...

    A work cell has four stations, and each unit produced at the cell needs to be processed by all of the stations in series. (The same unit cannot be worked on by four stations simultaneously.) The capacity of each station is (Station #, # of Machines, units per hour), (S1, 1, 4), (S2, 1, 5), (S3, 1, 6), (S4, 1, 8). What is the process time of the work cell in minutes per unit?

  • NEED ANSWER D. The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has...

    NEED ANSWER D. The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 2 Station 3 5 min/unit 12 min/unit Station 1 Machine B 12 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3....

  • The three stations work cell illustrated in the figure  below has a product that must go...

    The three stations work cell illustrated in the figure  below has a product that must go through one of the two machines at station 1 ( they are parallel) before proceeding  to station 2 Capacity:30 units/hrs Station 1 Machine A Station 1 Machine B Capacity:30 units / hrs Station 2 Capacity 12 units/hrs Station 3 Capacity 4 units/hrs A) The bottleneck time of the system is .......minutes per unit ( enter your response as  whole  number) B) Station 1 or...

  • (Process with Rework) Consider the following three-stage production process of glass ceramics, wh...

    Matching supply with Demand (3rd Edition) - Question 10.2 (Process with Rework) Consider the following three-stage production process of glass ceramics, which is operated as a worker-paced line. Q10.2 Components 6 min./unit 5 min./unit min. /unit Finished Units Rework The process is experiencing severe quality problems related to insufficiently trained work- ers. Specifically, 20 percent of the parts going through operation 1 are badly processed by the operator. Rather than scrapping the unit, it is moved to a highly skilled...

  • Exercise 10.10 (Job shop scheduling) A factory consists of m machines M1, , Mm, and needs to proc...

    Exercise 10.10 (Job shop scheduling) A factory consists of m machines M1, , Mm, and needs to process n jobs every day. Job j needs to be processed once by each machine in the order (M,a)M(m)). Machine M takes time Pij to process job j. A machine can only process one job at a time, and once a job is started on any machine, it must be processed to complet is to minimize the sum of the completion times of...

  • The three-station work cell illustrated in the figure below has a product that must go through...

    The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. a) The bottleneck time of the system is 6 minutos per unit (onitor your response as a whole number). b) Station 3 is the bottleneck station c) The throughout time is 13 minutes (onter your response as a whole number). d) If the firm operates 8 hours per...

  • A factory manufactures two products, each requiring the use of three machines. The first machine can...

    A factory manufactures two products, each requiring the use of three machines. The first machine can be used at most 70 hours; the second machine at most 40 hours; and the third machine at most 90 hours. The first product requires 2 hours on machine 1, 1 hour on machine 2, and 1 hour on machine 3; the second product requires 1 hour on machines 1 and 2 and 3 hours on machine 3. The profit is $40 per unit...

  • Consider a production line with three single-machine stations in series. Each has processing times with mean...

    Consider a production line with three single-machine stations in series. Each has processing times with mean two hours and standard deviation of two hours. a. Suppose we run this line as a push system and release jobs into it at a rate of 0.45 per hour with arrival variability given by Ca = 1. What is the average WIP in the line? b. Compute the throughput of this line if it is run as a CONWIP line with a WIP...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT