Consider a production line with three single-machine stations in series. Each has processing times with mean two hours and standard deviation of two hours.

a. Suppose we run this line as a push system and release jobs into it at a rate of 0.45 per hour with arrival variability given by Ca = 1. What is the average WIP in the line?

b. Compute the throughput of this line if it is run as a CONWIP line with a WIP level equal to your answer in (a). What is the throughput of the CONWIP line?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Processing time (Mean) = 2 hours

Standard deviation = 2 hours

Rate of jobs = 0.45 per hours

Utilization Server (u) =

= 0.015 per hour

Time spent in a station will be equal to

Given, Ca = 1

Thus, Time spent in a station (CT) = 2.091 hours

(a) Average WIP = CT * TH

= 2.091 * (2/60) = 0.068 Jobs

(b) TH = 2/60

= 0.033

Add a comment
Know the answer?
Add Answer to:
Consider a production line with three single-machine stations in series. Each has processing times with mean...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CONWIP & Push Systems

    Consider a production line with three single-machine stations in series. Each has processing times with mean 2 hours and standard deviation of 2 hours. Jobs are released at a rate of 0.45 jobs per hour. Also assume the arrivals are exponentially distributed. Suppose if this line has been run as a push system what is the average WIP in the line? Now if this line has been run as a CONWIP line with a WIP level equal to the previous...

  • (20) A flow line has two stations. The first station has a processing time of 6...

    (20) A flow line has two stations. The first station has a processing time of 6 minutes, and it has 3 servers. The second has a processing time of 11 minutes, and it has 4 servers. There is a constant arrival rate of jobs to the line What is the maximum utilization at each station? What assumptions do you need to ensure that maximum utilization is achieved? It turns out that the non-bottleneck station is very expensive, so management would...

  • A production station has a naturally occurring rate of unexpected breakdowns. The mean time between interruptions...

    A production station has a naturally occurring rate of unexpected breakdowns. The mean time between interruptions is 6 hours. The average repair time is 20 minutes, and the CV for repair time is 1.75. The mean natural processing time is 10 minutes with standard deviation 1 minute. a. What is the effective processing time and the CV of effective process time? b. If the arrival rate to the station is 5 jobs per hour, what is the station’s utilization? c....

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • 1. Consider a single workstation comprising one machine. (i) What will be the production rate of...

    1. Consider a single workstation comprising one machine. (i) What will be the production rate of this workstation, assuming all parts processed on it take (ii) Assume that the demand is 10/day, where the day has 8 working hours, what will be the (ii) What will be the utilization of the workstation given the demand in (ii)? 20 min? throughput? (iv) If a 2nd identical machine is added to the workstation, what will be the capacity of the workstation for...

  • You are setting up a production line and there are three potential line configurations. You have...

    You are setting up a production line and there are three potential line configurations. You have constructed a computer simulation of each set up. You have run 12 simulation runs of one month long for each simulation. It takes one hour to run a one month simulation on any line so you have invested 36 hours of simulation time already. You have calculated the statistics shown below on the throughput (parts/day) for your lines. Assuming that the throughput each day...

  • A manufacturing firm produces a single product using three different production lines. Each line has a...

    A manufacturing firm produces a single product using three different production lines. Each line has a different set of equipment because the age of cach line differs. They are considering changing the layout of the equipment to inerease output. First they take a sample of the amount of output produced under each line and each layout as show. Run a two way anova (Hint: you have to put in the data yourself in the proper format Line1 Line2 Line3 Layout1...

  • A manufacturing firm produces a single product using three different production lines. Each line has a...

    A manufacturing firm produces a single product using three different production lines. Each line has a different set of equipment because the age of each line differs. They are considering changing the layout of the equipment to increase output. First they take a sample of the amount of output produced under each line and each layout as show. Run a two way anoya.Hint: you have to put in the data yourself in the proper format Line1 Line2 Line3 Layout112 10...

  • A manufacturing firm produces a single product using three different production lines. Each line has different...

    A manufacturing firm produces a single product using three different production lines. Each line has different set of equipment because the age of each line differs. They are considering changing the layout of the equipment to increase output. First they take a sample of the amount of output produced under each line and each layout as show. Run a two way anoya (Hint: you have to put in the data yourself in the proper format Line1 Line2 Line3 12 14...

  • 1. Many companies use a incoming shipments of parts, raw materials, and so on. In the...

    1. Many companies use a incoming shipments of parts, raw materials, and so on. In the electronics industry, component parts are commonly shipped from suppliers in large lots. Inspection of a sample of n components can be viewed as the n trials of a binomial experimem. The outcome for each component tested (trialD will be that the component is classified as good or defective defective components in the lot do not exceed 1 %. Suppose a random sample of fiver...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT