Question

Question Help Consider the following information: Demand rate (D) = 1,500 units per hour Lead time (T) = 7 hours Container ca
0 0
Add a comment Improve this question Transcribed image text
Answer #1

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****

(a)

N = DT(1+X) / C = [1500*7(1+0.2)] / 220 = 630 / 11 = 57.27 = 57

(b)

NC/ D = 57.27*220 / 1500 = 8.3996 = 8.4

(c)

Removing the safety factor

N = [1500*7(1+0)] / 220 = 525 / 11 = 47.72 = 48

Hours worth of demand = 48*220 / 1500 = 176 / 25 = 7.04 = 7

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****

Add a comment
Know the answer?
Add Answer to:
Question Help Consider the following information: Demand rate (D) = 1,500 units per hour Lead time...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following information: Demand rate (D) = 270 units per hour Lead time (T) =...

    Consider the following information: Demand rate (D) = 270 units per hour Lead time (T) = 10 hours Container capacity (C) = 30 units Safety factor (x) = 10% a. The number of kanban production cards is (Enter your response rounded up to the next whole number.)

  • Please solve in excel with all formulas shown You have the following information: 5. Demand rate...

    Please solve in excel with all formulas shown You have the following information: 5. Demand rate = 250 units per hour Lead time = 15 hours Container capacity 300 units Safety stock = 20% Determine the number of Kanban cards required. a. Convert these Kanban cards into the number of hours b. of demand they represent If the container size is reduced from 300 to 150 units C what impact, if any, will it have on inventory levels?

  • A bottling plant fills 2,400 bottles every two hours. The lead time is 50 minutes and...

    A bottling plant fills 2,400 bottles every two hours. The lead time is 50 minutes and a container accommodates 80 bottles. The safety stock is 30 percent of expected demand. How many kanban cards are needed? (Round up your answer to the next whole number.) Number of kanban card sets

  • JIT /Lean - Kanban: Daily demand for a product is 200 units. The production lead time...

    JIT /Lean - Kanban: Daily demand for a product is 200 units. The production lead time (wait time + production time) for a container is 2 days. A 1-day safety stock is kept. How many kanban containers will be needed if each container holds 50 units? [Show calculations.]

  • Answers must be to rounded to the nearest number Markland First National Bank of Rolla utilizes...

    Answers must be to rounded to the nearest number Markland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 25 checks and spends 48 minutes a day in processing and 4 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen contingencies of 0.20. units. (Enter your response rounded to...

  • Given this information: Lead-time demand = 620 pounds Standard deviation of lead time demand = 50...

    Given this information: Lead-time demand = 620 pounds Standard deviation of lead time demand = 50 pounds (Assume normality.) Acceptable stockout risk during lead time = 4 percent Use Table. a. What amount of safety stock is appropriate? (Round your answer to the nearest whole number.)   Safety stock units b. When should this item be reordered? (Round your answer to the nearest whole number.)   ROP units c. What risk of stockout would result from a decision not to have any...

  • Given this information: Expected demand during lead time = 285 units Standard deviation of lead time...

    Given this information: Expected demand during lead time = 285 units Standard deviation of lead time demand = 16 units Use Table. Determine each of the following, assuming that lead time demand is distributed normally: a. The ROP that will provide a risk of stockout of 1 percent during lead time. (Round your answer to the nearest whole number.) ROP _____ units    b. The safety stock needed to attain a 1 percent risk of stockout during lead time. (Do...

  • Given this information: Expected demand during lead time = 295 units Standard deviation of lead time...

    Given this information: Expected demand during lead time = 295 units Standard deviation of lead time demand = 20 units Use Table. Determine each of the following, assuming that lead time demand is distributed normally: a. The ROP that will provide a risk of stockout of 2 percent during lead time. (Round your answer to the nearest whole number.) ROP             units    b. The safety stock needed to attain a 2 percent risk of stockout during lead time....

  • b. If the muda or waste in the system were eliminated completely, how many containers would...

    b. If the muda or waste in the system were eliminated completely, how many containers would be needed? Markland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 50 checks and spends 24 minutes a day in processing and 2 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen...

  • Kanban container size = 63 units (round your response to the nearest whole number). Number of...

    Kanban container size = 63 units (round your response to the nearest whole number). Number of kanbans needed = kanbans (round your response to the nearest whole number). Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $30 Annual holding cost $120 per subassembly Daily production 30 subassemblies Annual usage 4,000 (50 weeks 5 days each x daily...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT