You are required to schedule helpers so that you have sufficient helpers during the event and with the lowest cost. The event will start from 9am to 5pm. Based on your past experience, the number of helpers required in each hour is as below:
Time |
Number of helpers |
9am – 10am |
3 |
10am – 11am |
3 |
11am – 12pm |
6 |
12pm – 1pm |
8 |
1pm – 2pm |
6 |
2pm – 3pm |
4 |
3pm – 4pm |
3 |
4pm – 5pm |
3 |
Only 2 of your friends will be coming to help during the event. One of them comes at 9am, works for 3 hours, takes an hour off and returns for another 4 hours. Another friend comes at 12pm and works for 4 hours. Besides, part-time helpers are also required and they work for 3-hour shift beginning on the hour.
Assume each part-time helpers is paid $10 each hour, you are required to determine how many part-time helpers required so that the cost can be mininised. Based on your output, develop a schedule to show the allocation of part-time helpers.
This question is to answer using linear programming. Please solve for sample answer for me. Thanks.
Answer:
Integer linear program is following:
Let
X1 be the number of part-time helpers starting on at 9 am
X2 be the number of part-time helpers starting on at 10 am
X3 be the number of part-time helpers starting on at 11 am
X4 be the number of part-time helpers starting on at 12 pm
X5 be the number of part-time helpers starting on at 1 pm
X6 be the number of part-time helpers starting on at 2 pm
Minimize 3*10*(X1+X2+X3+X4+X5+X6)
s.t.
X1 >= 3-1
X1+X2 >= 3-1
X1+X2+X3 >= 6-1
X2+X3+X4 >= 8-1
X3+X4+X5 >= 6-1-1
X4+X5+X6 >= 4-1-1
X5+X6 >= 3-1-1
X6 >= 3-1
X1, X2, X3, X4, X5, X6 integers
Solution using LINGO is following:
Optimal solution:
X1 = 2
X2 = 3
X3 = 4
X4 = 0
X5 = 0
X6 = 2
Total cost = $ 330
THANK YOU!
You are required to schedule helpers so that you have sufficient helpers during the event and...
Question 3 The following table shows the staffing requirements for a restaurant at different hours. Assume each staff member works four-hour shifts. 8am 9am 10am 11am Noon 1pm 2pm 3pm 4pm 5pm 6pm 7pm Requirements 2 3 5 8 8 6 5 8 8 6 4 3 Use the first-hour principle to find the personnel schedule. For each hour, determine the amount of workers that should be assigned, the amount that are on duty and the amount of excess staff....
human benefits offered. The starting salary is $30.000 pervescente resources at 555-555-5555 to apply 41. Using the employment advertisement above, which of the following applicants could meet the requirements of this job? a. A writer looking for 40 hours a week. b. A college graduate who majored in lay out design c. A newspaper reporter who has two years of experience d. A teacher who has taught for 4 years 42. Everyone had to drive slowly because of the high...
PARTI Introduction The endocrine system consists of a group of glands located all around the body that produce and secrete chemical messengers. These messengers or hormones, travel through the blood stream causing effects in specific target tissues. The endocrine system serves as a fine tuner for maintaining the equilibrium in the body of many intermal parameters like body temperature, blood pH, blood glucose (this is the concept of homeostasis). This system, combined with the nervous system, serves to control all...
Western Family Steakhouse offers a variety of low-cost meals and quick service. Other than management, the steakhouse operates with two full-time employees who work 8 hours per day. The rest of the employees are part-time employees who are scheduled for 4-hour shifts during peak meal times. On Saturdays the steakhouse is open from 11:00 A.M. to 10:00 P.M. Management wants to develop a schedule for part-time employees that will minimize labor costs and still provide excellent customer service. The average...
Western Family Steakhouse offers a variety of low-cost meals and quick service. Other than management, the steakhouse operates with two full-time employees who work 8 hours per day. The rest of the employees are part-time employees who are scheduled for 4-hour shifts during peak meal times. On Saturdays the steakhouse is open from 11:00 A.M. to 10:00 P.M. Management wants to develop a schedule for part-time employees that will minimize labor costs and still provide excellent customer service. The average...
Western Family Steakhouse offers a variety of low-cost meals and quick service. Other than management, the steakhouse operates with two full-time employees who work 8 hours per day. The rest of the employees are part-time employees who are scheduled for 4-hour shifts during peak meal times. On Saturdays the steakhouse is open from 11:00 A.M. to 10:00 P.M. Management wants to develop a schedule for part-time employees that will minimize labor costs and still provide excellent customer service. The average...
Problem 4-25 (Algorithmic)Western Family Steakhouse offers a variety of low-cost meals and quick service. Other than management, the steakhouse operates with two full-time employees who work 8 hours per day. The rest of the employees are part-time employees who are scheduled for 4-hour shifts during peak meal times. On Saturdays the steakhouse is open from 11:00 A.M. to 10:00 P.M. Management wants to develop a schedule for part-time employees that will minimize labor costs and still provide excellent customer service....
Project. Workforce Planning Mexico City Bank of Commerce and Industry is a busy bank that needs different number of tellers depending on the time of day due to different numbers of customers needed service. The table below indicates the number of workers eeded at various hours that the bank is open. Time Period # of Tellers Needed Time Period # of Tellers Needed 9 a.m.–10 a.m. 10 1 p.m.–2 p.m. 18 10 a.m.–11 a.m. 12 2 p.m.–3 p.m. 16 11...
Problems 1-10 Now you have another piece of information - Table 1. It was either obtained by measuring times to complete each operation, or based on experience with similar operations. For simplicity, setup and cycle times are assumed the same for both 1 and 10.000 parts. To simplify calculations, and without loss of generality, the following is assumed: - The material cost per one part is assumed to be the same, so we neglect it for comparison purposes - Tool...
The bank is working to develop an efficient work schedule for full-time and part-time tellers. The schedule must provide for efficient operation of the bank, including adequate customer service, employee breaks, and so on. On Fridays, the bank is open from 9:00 A.M. to 7:00 P.M. The number of tellers necessary to provide adequate customer service during each hour of operation is summarized here. Time No. of Tellers Time No. of Tellers 9:00 a.m.-10:00 a.m. 6 2:00 p.m.-3:00 p.m. 7...